Yaprak Weir and HEPP
#90of 295 in Turkey#204of 1339 in Verra (VCS)#140of 806 in AMS-I.D
Audit Analysis
The Yaprak Weir and HEPP is a small-scale hydro project under VCS AMS-I.D. with VVB-confirmed additionality and no reversal risk, but it carries a project-specific baseline (with a contradiction in the monitoring report), a 2012 grid emission factor, and 13 material findings related to documentation completeness. The project delivered approximately 91% of its ex-ante credit estimate over the crediting period, with no over-crediting detected.
Red Flags
- 13 material findings (CARs) in the verification report covering missing project details, invalid guideline references, and incomplete additionality documentation
- Baseline method contradiction: verification report states 'project' while the monitoring report states 'jurisdictional'
- Grid emission factor of 0.4855 is from 2012 and has not been updated in the available documents
- Minimum extraction confidence is low, indicating at least one key document was poorly readable
- CORSIA eligibility and CCP status are not stated in any available document
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 40 | 0 | 40 | |
| 2018 | 2,062 | 2,062 | 0 | |
| 2019 | 46 | 46 | 0 | |
| 2021 | 730 | 730 | 0 | |
| Total | 2,878 | 2,838 | 40 |
Risk Indicators
Combined test, VVB-confirmed
Hydro – no reversal risk
Quantified at 0%, justified for hydro
Project-specific; doc contradiction
Grievance & benefit sharing present; FPIC not stated
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →