Yaysun-MT Solar Power Project
#322of 1935 in Renewable energy#71of 295 in Turkey#165of 1339 in Verra (VCS)#244of 1287 in ACM0002
Audit Analysis
The Yaysun-MT Solar Power Project is a VCS-registered renewable energy project in Turkey with a VVB-verified investment additionality test and no reported reversal events. However, the absence of a buffer pool, a project-specific baseline with a 2017 grid emission factor, and a significant discrepancy between the 40,618 tCO₂ verified in the 2025 verification report and the 81,478 tCO₂ cited in the 2024 monitoring report introduce moderate uncertainty. Low extraction confidence across the document set and numerous (though resolved) validation findings further temper confidence in the overall data quality.
Red Flags
- ERR figure discrepancy: the 2025 verification report confirms 40,618 tCO₂ while the 2024 monitoring report cites 81,478 tCO₂ — a factor-of-two gap that is not explained in the extracted record
- The monitoring report is dated 2024-02-23, which precedes the stated end of the monitoring period (2024-03-31), raising questions about whether the full period was captured
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable and the structured data may be incomplete
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2018 | 4,322 | 0 | 4,322 | |
| 2019 | 22,738 | 0 | 22,738 | |
| 2020 | 22,863 | 0 | 22,863 | |
| 2021 | 23,316 | 0 | 23,316 | |
| 2022 | 21,773 | 0 | 21,773 | |
| 2023 | 22,621 | 0 | 22,621 | |
| 2024 | 4,463 | 0 | 4,463 | |
| Total | 122,096 | 0 | 122,096 |
Risk Indicators
VVB-verified investment test
mixed evidence / unresolved risk
Quantified at 0%, appropriate for solar
Project-specific, 2017 grid EF, no reassessment yet due
FPIC, grievance mechanism, safeguards documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →