60 MW Bandirma Wind Power Plant Project

GS-1170 ↗

4.3 / 10
Integrity
4.8
Transparency
4.1
Claim Safety
4.3
Documentation
3.2

Score Breakdown

Integrity

verified Additionality was confirmed by the VVB under an investment test, which supports the project’s core eligibility.

missing Leakage is marked as not addressed in the latest verification report, and reversal handling is also not addressed.

Transparency

verified The project has a named verifier, Applus+ Certification, and a defined monitoring period in the 2025 verification report.

missing The extracted record does not show claimed versus verified ER totals, and key monitoring methods such as usage monitoring and FNRB are not stated.

Claim Safety

verified The project is a wind project using ACM0002 with a project baseline, which is generally lower risk than more discretionary baseline approaches.

missing The latest report contains unresolved leakage and reversal questions, and the project is marked CORSIA-eligible, which keeps dual-claim risk elevated.

Documentation

verified The record includes a recent verification report, a named VVB, and a large number of extracted facts across official documents.

missing Extraction confidence is low, and the verification report lists many CARs and CRs plus missing monitoring details, indicating incomplete documentation.

Detailed Analysis

Integrity

The project has a meaningful positive signal because the verification report confirms additionality through an investment test and names Applus+ Certification as the VVB. However, the latest report also says leakage is not addressed and reversal events are not addressed, while the material findings and corrective actions show multiple unresolved monitoring and reporting issues. I therefore score integrity below average despite the renewable-energy context.

Transparency

Transparency is weakened by missing core MRV fields in the extracted record, including no stated usage monitoring method, no verified or claimed ER totals, and no FNRB information. The monitoring period is clear and the verifier is identified, but the report also contains many corrective actions for missing records and calculations. The low extraction confidence further reduces confidence in the completeness of the public record.

Claim Safety

Claim safety is moderate at best because the project uses a standard wind methodology and a project baseline, which is generally a defensible setup. Still, the latest verification report leaves leakage unresolved, and the record is inconsistent on reversal handling and crediting-period timing. Because the project is marked CORSIA-eligible and CCP status is not stated, dual-claim risk is not fully excluded.

Documentation

Documentation quality is limited by low extraction confidence and by the fact that the latest verification report lists numerous CARs and CRs, including missing sustainability monitoring parameters, meter evidence, and SDG calculations. The project does have a recent verification report and a named VVB, but the record does not show a complete, clean evidence trail. The contradiction on the crediting period also suggests the documentation set is not fully harmonized.

Overall

I privileged the latest verification report dated 2025-01-02 for leakage, reversal status, and documentation quality because it is the most recent and specific source, even though an earlier report said leakage was negligible and none reported. I also privileged the later crediting-period statement in the extracted record, but the contradiction with the earlier period indicates the record is not fully consistent and lowers confidence. Given the many unresolved CARs/CRs, low extraction confidence, and missing MRV fields, the project looks plausible but not high quality from a claims perspective.

Audit Analysis

This is a wind project with VVB-confirmed additionality and a recent verification report, but the evidence set shows several documentation gaps and unresolved issues around leakage, reversals, and monitoring completeness. The project appears operationally credible, yet the record quality is uneven and the contradictions reduce confidence in the claimed emissions reductions.

Project Description

Developer: BORUSAN ENBW ENERJI YATIRIMLARI VE ÜRETIM A.S. Type: Wind Size: Large Scale Methodology: ACM0002 Grid-connected electricity generation from renewable sources Crediting period: 2015-07-24 → 2029-07-23 Estimated annual credits: 108692 tCO2e SDGs: Goal 13: Climate Action, Goal 8: Decent Work and Economic Growth, Goal 6: Clean Water and Sanitation, Goal 7: Affordable and Clean Energy

Red Flags

  • Leakage is not addressed in the latest verification record, despite an earlier document saying it was negligible.
  • The latest report lists many corrective actions and material findings, including missing monitoring records and SDG-related calculations.
  • The crediting period and reversal status are inconsistent across documents, which weakens reliability.

Credit Vintages

Issued Retired Available
2015
50,830 50,830 0
2016
123,310 123,310 0
2017
112,511 94,690 17,821
2018
117,354 86,368 30,986
2019
119,902 19,902 100,000
2020
119,700 100,591 19,109
2021
116,038 87,654 28,384
2022
123,631 0 123,631
2023
126,725 28,706 98,019
Total 1,010,001 592,051 417,950

Cosa migliorerebbe questo punteggio

  • Provide a complete, reconciled monitoring package with verified and claimed ER totals, meter evidence, and all sustainability parameters.
  • Resolve the leakage, reversal, and crediting-period contradictions with a single authoritative statement from the latest registry and verification documents.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

No reversal treatment stated

Leakage

Latest report does not address leakage

Baseline

Project baseline with reassessment timing unclear

Safeguards

FPIC and grievance mechanism present

Double-claim

CORSIA-eligible; CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-19 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti