Anshan Iron and Steel Group Corporation (Yingkou) Coke Dry Quenching Power Generation Project
#73of 204 in China#46of 213 in CDM (UNFCCC)#4of 17 in ACM0004
Audit Analysis
A CDM energy-efficiency own-generation project (ACM0004 v2) with VVB-verified combined additionality and a jurisdictional baseline, but undermined by four material findings (including IRR recalculation and PDD inconsistencies), three cross-document contradictions, and the absence of a buffer pool or verified ERR figure. The project delivered roughly 263% of its pro-rata expectation in the first monitoring period, which is conservative, but the documentation gaps and unresolved data fields limit confidence in the overall credit quality.
Red Flags
- Four material findings in the verification report, including changes to the IRR calculation and common-practice analysis (CAR 10, 11), which directly affect the additionality finding
- No buffer pool percentage or reversal-event data found in any available document, leaving permanence risk unquantified for a 10-year crediting period
- Verified ERR figure is not stated in the extracted record, preventing an independent check of the project's actual delivery against its claim
- Baseline method is characterised as 'project' in the 2010 monitoring report but 'jurisdictional' in the 2009 validation report — an unresolved contradiction that affects baseline credibility
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 35,623 | 0 | 35,623 | |
| Total | 35,623 | 0 | 35,623 |
Risk Indicators
Combined test, VVB-verified
No buffer pool or reversal data
Quantified, 0% deduction justified
Jurisdictional but cross-doc contradiction
Mentioned but no FPIC or grievance detail
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →