Re-assessment pending
Beijing No.3 Thermal Power Plant Gas-Steam Combined Cycle Project Using Natural Gas
- Standard
- CDM
- Methodology
- AM0029 (CDM)
- Registry
- CDM-1373 ↗ · Registered
- Country
- China
- Credit type
- Fossil fuel switch
Beijing No.3 Thermal Power Plant Gas-Steam Combined Cycle Project Using Natural Gas (CDM-1373) is being re-assessed under the current CarbonMeld methodology (v3): its earlier rating came from an older version of the method and is no longer shown, so this page gives no CarbonMeld rating until the new analysis is published.
Assessment
Being reassessed under the current method
The earlier analysis of this project used an older version of our method, so its rating is no longer shown: it is not comparable with ratings under the current method (v3). The new analysis will appear here once it is published; until then, this page shows the project's registry data.
Standard and methodology
Evidence
Eligibility & market
Under decision 4/CMP.20 of the Parties to the Kyoto Protocol (FCCC/KP/CMP/2025/7/Add.1, paragraph 5), the submission of requests for issuance of new CERs was discontinued as of 30 June 2026; requests to transfer CERs to the Article 6.4 mechanism registry, cancellations and any other transactions in the CDM registry are discontinued as of 31 December 2026. This page keeps the project's record.
What can you claim with this credit?
Four checks buyers ask about, from the registry and the Integrity Council (ICVCM).
Airlines (CORSIA)
Not published
This registry does not publish CORSIA eligibility per project.
Integrity label (ICVCM CCP)
No ICVCM information
No CCP label and no ICVCM decision found for this project's methodology.
Removal or reduction
Emission reduction or avoidance
Prevents or reduces emissions — fits contribution claims, not SBTi neutralisation.
Source: project sector
Covers: the project type, not a label on individual credits
Paris Agreement (Article 6)
Not published
This registry does not publish Article 6 authorizations.
Information only, from public sources. Claim rules (CORSIA, SBTi, EU rules on green claims) change: check them before making a public claim. Since 27 September 2026, EU consumer rules do not allow “climate neutral” product claims based on offsets.
Credit Issuances
| Issued | Retired | Available | ||
|---|---|---|---|---|
| Issued in 2009 | 386,613 | 0 | 386,613 | |
| monitoring period 15 Feb 2008 – 30 Jun 2008 | ||||
| Issued in 2010 | 290,902 | 0 | 290,902 | |
| monitoring period 1 Jul 2008 – 31 Oct 2008 | ||||
| Issued in 2011 | 1,140,466 | 0 | 1,140,466 | |
| monitoring periods 1 Nov 2008 – 31 Mar 2010 | ||||
| Issued in 2012 | 628,350 | 0 | 628,350 | |
| monitoring periods 1 Apr 2010 – 31 Mar 2011 | ||||
| Total | 2,446,331 | 0 | 2,446,331 | |
The registry publishes each issuance with its monitoring period. Each row here is the sum of one year's issuances, by the year they were issued — not a vintage (the year the reductions or removals took place). Under each year: the monitoring periods of the credits issued in it.
Where to buy
Got an offer for these credits? Check it against the registry →
+ Know where to buy this?
Listing multiple projects? Send us a CSV at listings@carbonmeld.com.
Profile & governance
Are you the project owner?
Full analysis (free for owners)
Owners get free access to the full analysis of their own project: every rule that raised or lowered the number, with the fact and the source it rests on, the negative facts' detail and the documents read. Write to us from your organisation's email address.
hello@carbonmeld.com →Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the rating.
hello@carbonmeld.com →Report an error on this page
Something wrong in the analysis, or a registry document we have not used? Send us the link to the public source: you get a reference and an answer within 30 days.
Report an error on this page →Cite this page
CarbonMeld (2026). Beijing No.3 Thermal Power Plant Gas-Steam Combined Cycle Project Using Natural Gas (CDM-1373): registry data. https://carbonmeld.com/projects/beijing-no-3-thermal-power-plant-gas-steam-combined-cycle-project-using-natural-/.
The citation names the registry data this page shows; the page gives no CarbonMeld rating.
Similar projects
Same methodology or sector, the same registry first.
- Natural gas based combined cycle power plant in Tripura, IndiaCDM-6888
- UNOSUGEN Natural gas based grid connected Combined cycle power generation projectCDM-8048
- Zhumadian Zhongyuan Gas-Steam Combined Cycle Power Project in Henan ChinaCDM-2344
- Grid connected electricity generation plant using natural gas at Jurong Island in SingaporeCDM-9687
- Huadian Guangzhou Higher Education Mega Center LNG-fired Power Generation Project in ChinaCDM-3786
- Grid Connected Gas based Combined Cycle Power Project in Andhra PradeshCDM-8323
- Grid connected natural gas based power project in Raigad District, Maharastra, IndiaCDM-9124
- OML58 IPP Gas Fired Generation ProjectCDM-9391