Biogas Support Program - Nepal Activity-3

CDM-5415 ↗

#33of 111 in Biogas#7of 14 in Nepal#75of 213 in CDM (UNFCCC)

5.2/ 10
Integrity
5.5
Transparency
5.5
Claim Safety
4.0
Documentation
6.0

Audit Analysis

A CDM biogas methane-avoidance project in Nepal with a barrier additionality test, a 5% quantified leakage deduction, and a project-specific baseline reassessed in 2019. The project carries moderate data-reliability concerns due to a significant discrepancy in claimed ERR between two monitoring reports (64,201 vs 94,348 tCO₂e) and a 14-percentage-point gap between the assumed (100%) and verified (85.71%) usage rate. Six material findings and five corrective actions were raised during verification, all relating to initial documentation gaps that were subsequently addressed.

Red Flags

  • Claimed ERR of 64,201 tCO₂e in the 2022 monitoring report contradicts 94,348 tCO₂e in an earlier monitoring report (Feb 2021), a 47% discrepancy that undermines confidence in the project's quantification
  • Usage rate assumed at 100% in the monitoring report versus 85.71% verified, a 14.3-percentage-point overstatement that inflates the baseline reduction estimate
  • Buffer pool percentage and reversal-event history are not stated in any available document, leaving CDM permanence risk unquantified
  • Six material findings and five corrective actions were raised during verification, indicating the initial PDD and monitoring framework required substantial correction before approval

Credit Vintages

IssuedRetiredAvailable
2014
100,6410100,641
2015
64,314064,314
2016
66,297066,297
2017
61,452061,452
2018
54,403054,403
2019
74,622074,622
2020
45,678045,678
2021
94,347094,347
Total561,7540561,754

Risk Indicators

Additionality

Barrier test applied; VVB sign-off not confirmed in record

Permanence

Buffer pool and reversal history not stated

Leakage

5% quantified deduction in monitoring report

Baseline

Project-specific baseline; reassessed 2019

Safeguards

Grievance mechanism and safeguards mentioned; FPIC not confi

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-26General Methodology v2.0

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents