Biogas Support Program - Nepal Activity-3
#33of 111 in Biogas#7of 14 in Nepal#75of 213 in CDM (UNFCCC)
Audit Analysis
A CDM biogas methane-avoidance project in Nepal with a barrier additionality test, a 5% quantified leakage deduction, and a project-specific baseline reassessed in 2019. The project carries moderate data-reliability concerns due to a significant discrepancy in claimed ERR between two monitoring reports (64,201 vs 94,348 tCO₂e) and a 14-percentage-point gap between the assumed (100%) and verified (85.71%) usage rate. Six material findings and five corrective actions were raised during verification, all relating to initial documentation gaps that were subsequently addressed.
Red Flags
- Claimed ERR of 64,201 tCO₂e in the 2022 monitoring report contradicts 94,348 tCO₂e in an earlier monitoring report (Feb 2021), a 47% discrepancy that undermines confidence in the project's quantification
- Usage rate assumed at 100% in the monitoring report versus 85.71% verified, a 14.3-percentage-point overstatement that inflates the baseline reduction estimate
- Buffer pool percentage and reversal-event history are not stated in any available document, leaving CDM permanence risk unquantified
- Six material findings and five corrective actions were raised during verification, indicating the initial PDD and monitoring framework required substantial correction before approval
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 100,641 | 0 | 100,641 | |
| 2015 | 64,314 | 0 | 64,314 | |
| 2016 | 66,297 | 0 | 66,297 | |
| 2017 | 61,452 | 0 | 61,452 | |
| 2018 | 54,403 | 0 | 54,403 | |
| 2019 | 74,622 | 0 | 74,622 | |
| 2020 | 45,678 | 0 | 45,678 | |
| 2021 | 94,347 | 0 | 94,347 | |
| Total | 561,754 | 0 | 561,754 |
Risk Indicators
Barrier test applied; VVB sign-off not confirmed in record
Buffer pool and reversal history not stated
5% quantified deduction in monitoring report
Project-specific baseline; reassessed 2019
Grievance mechanism and safeguards mentioned; FPIC not confi
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →