Vai al contenuto principale
GS Solar Thermal - Electricity Turkey Documentazione completa General Methodology v2.0

Corum Solar Power Plant Project

GS-1418 ↗

4.3 / 10
Integrity
4.4
Transparency
4.8
Claim Safety
4.2
Documentation
3.1

Score Breakdown

Integrity

missing The extracted monitoring report does not show additionality being confirmed by the VVB, and the contradiction log shows an earlier document dated 2021-12-14 indicating it was true, so I privileged the later 2022-11-23 record as the more recent source.

verified No reversal events were reported, and the project is a solar electricity activity with a stated leakage deduction of 0% and a claim that leakage is negligible.

Transparency

verified The monitoring period is clearly stated for 2024-04-01 to 2024-12-31, and the VVB is identified as RINA Services S.p.A. (RINA).

missing The extracted record does not provide total ERs claimed or verified, and the low extraction confidence suggests at least one key document was difficult to read.

Claim Safety

missing The baseline is project-specific rather than a more conservative standardized or jurisdictional baseline, which weakens over-crediting protection.

inferred The project is marked as not CORSIA-eligible, while CCP status is not mentioned; the contradiction log also shows a change in grid emission factor and crediting period across documents, which adds uncertainty.

Documentation

verified Multiple official documents were used, and the record includes a named VVB plus a defined monitoring period and crediting period.

missing The extraction confidence is low, evidence documents are not clearly enumerated, and the verification/validation history shows many corrective actions and at least one discrepancy in electricity generation cross-checks.

Detailed Analysis

Integrity

The project has some integrity positives, including no reported reversal events and a stated leakage deduction of 0% with leakage described as negligible in the monitoring report dated 2024-11-12. However, additionality is not confirmed by the VVB in the extracted record, and the contradiction log shows an earlier document dated 2021-12-14 indicating the opposite; I privileged the later 2022-11-23 record because it is more recent. The monitoring report also notes a minor discrepancy between electricity generation sources and multiple corrective actions, which weakens confidence in the emissions claim.

Transparency

Transparency is moderate because the monitoring period is clearly stated and the VVB is named as RINA Services S.p.A. (RINA). That said, total ERs claimed and verified are not found in the extracted record, and the low extraction confidence indicates at least one key document was poorly readable. The absence of a clearly stated FNRB method also leaves a gap in the public MRV picture, even though this is a renewable electricity project rather than a land-use project.

Claim Safety

Claim safety is limited by the project-specific baseline method and the lack of a quantified, well-supported leakage treatment beyond a 0% deduction. The project is marked as not CORSIA-eligible, which helps reduce dual-market concern, but CCP status is not mentioned. The contradiction log also shows changes in grid emission factor and crediting period across documents; I privileged the later values because they are more recent, but the inconsistency still increases over-crediting risk.

Documentation

Documentation quality is weak to moderate. The record includes a named VVB, a monitoring period, a crediting period, and multiple official documents, but the extracted evidence list is not clearly populated and the extraction confidence is low. The validation and verification history shows many corrective actions, and the monitoring report records a discrepancy in net electricity generation cross-checks, which suggests the file set is not fully clean or easy to audit.

Overall

Overall, this is a middling-quality project file with some operational safeguards but notable evidence gaps and reliability issues. I addressed the contradictions by privileging the more recent documents for additionality, leakage, reversal status, grid emission factor, and crediting period, while still penalizing the score because the inconsistencies themselves reduce trust. The documentation score is especially constrained by low extraction confidence, and under the stated gate rules a low documentation score would also cap transparency if it fell below 3.0; integrity remains above the 4.0 gate threshold, so no overall cap is triggered.

Audit Analysis

The project has some positive safeguards and monitoring elements, but the evidence base is thin and several key items are either not stated or internally inconsistent. Additionality was not confirmed by the VVB in the extracted record, leakage treatment is weakly supported, and the low extraction confidence reduces trust in the documentation.

Project Description

Developer: Galata Wind Enerji A.S. Type: Solar Thermal - Electricity Size: Small Scale Methodology: AMS-I.D. Grid connected renewable electricity generation Crediting period: 2017-12-19 → 2027-12-18 Estimated annual credits: 7 tCO2e SDGs: Goal 13: Climate Action, Goal 8: Decent Work and Economic Growth, Goal 7: Affordable and Clean Energy

Red Flags

  • Additionality is not confirmed by the VVB in the extracted record, and the contradiction log shows an earlier document indicating the opposite.
  • Several core data points are missing or weakly supported, including total ERs claimed/verified, buffer pool coverage, and a quantified leakage rationale.
  • The monitoring report records multiple corrective actions and a minor discrepancy in electricity generation sources, which raises reliability concerns.

Credit Vintages

Issued Retired Available
2017
103 103 0
2018
7,688 355 7,333
2019
7,717 1,253 6,464
2020
8,035 160 7,875
2021
7,491 149 7,342
2022
7,183 0 7,183
2023
8,866 0 8,866
2024
1,539 0 1,539
Total 48,622 2,020 46,602

Cosa migliorerebbe questo punteggio

  • Provide a clean, reconciled set of validation and verification documents showing the final additionality determination, baseline rationale, and the exact ERs claimed versus verified.
  • Add a quantified leakage assessment, clearer cross-checks for electricity generation, and a complete registry/public disclosure package with readable source documents.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

test present, VVB confirmation unclear

Permanence

no reversal events reported

Leakage

0% deduction with limited support

Baseline

project baseline, reassessment timing known

Safeguards

FPIC and grievance mechanism present

Double-claim

not CORSIA-eligible; CCP not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-19 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti