Vai al contenuto principale
GS Solar Thermal - Electricity China Documentazione completa General Methodology v2.0

Dongdongtan 9MWp Solar PV Project

GS-1332 ↗

5.1 / 10
Integrity
5.2
Transparency
5.5
Claim Safety
4.5
Documentation
5.0

Score Breakdown

Integrity

verified Additionality confirmed by the VVB (Shenzhen CTI) and recorded investment test (verification report, 2024-11-12).

missing Leakage not adequately justified (documents state leakage justification is not addressed) and buffer pool percentage not stated.

Transparency

verified VVB name and a recent monitoring period (2024) are provided; monitoring via smart meters is described.

missing Key verification numbers are missing: total emissions reductions verified is not stated and evidence documents are labelled unknown.

Claim Safety

verified Uses a recognised methodology (AMS I.D. v3.0) and grid emission factor is reported (0.856875).

missing Leakage deduction of 0% lacks documented justification and national FNRB data not applicable or not provided, increasing over‑crediting risk.

Documentation

verified A recent validation/verification document date is present (2024-11-12) and 17 documents were used.

missing Minimum extraction confidence is only medium and evidence documents are unspecified or labelled unknown.

Detailed Analysis

Integrity

The verification report by Shenzhen CTI (document dated 2024-11-12) confirms additionality via an investment test, which supports basic integrity. However, the project shows a 0% leakage deduction while the latest documents state leakage justification is not addressed, and the buffer pool percentage is not provided in the extracted record—these are material weaknesses. Several corrective actions and clarification requests were raised and closed (listed in the validation/verification materials), which indicates issues were found and remediated but reduces confidence in robustness.

Transparency

Project transparency is mixed: the VVB is named and a current monitoring period (2024-01-01 to 2024-12-31) and smart meter monitoring are documented, which helps traceability. But total emissions reductions verified is not provided in the extracted record (total_err_verified missing), evidence documents are listed as 'unknown', and extraction confidence is only medium, limiting transparency.

Claim Safety

The project uses an established methodology (AMS I.D. v3.0) and reports a grid emission factor (0.856875), which supports claim defensibility. Conversely, leakage treatment is weak (0% deduction without documented justification in the latest documents) and national/regional factors (FNRB) are not applicable or absent, raising over‑crediting risk. CORSIA/CCP status is not stated, so dual‑claim risk cannot be ruled out.

Documentation

Documentation breadth is moderate: 17 documents were used and the most recent document date is 2024-11-12 with a named VVB. However, evidence documents are not clearly identified (listed as 'unknown') and extraction confidence is medium, indicating some source reliability issues. Multiple corrective actions were required and closed; that is positive for follow-up but the original issues lower documentation quality.

Overall

I privileged the more recent and more specific document entries when contradictions occurred. For additionality test type I privileged the 2022-11-11/2022-05-07 era confirmation that the test is investment-based (prefer the 2022 record over 2014 as more recent). For benefit sharing, I accepted the 2022 record that benefit sharing is not described rather than the 2014 record that it was; the later document is treated as authoritative. For leakage, I privileged the later 2022 entry stating leakage is not addressed over an earlier 2020 note that deemed leakage negligible; the absence of a justification in the later documents reduces scores. For reversal events I accepted the 2024 statement that none were reported. For crediting period, I privileged the later 2022-11-11 record showing the 2013–2020 period over an earlier 2022-05-07 note suggesting 2020–2027, because the 2022-11-11 entry is later and explicitly appears in the validation materials. These contradictions and the medium extraction confidence reduce overall reliability and pull scores down despite VVB confirmation of additionality. The composite weighted score is 5.1.

Audit Analysis

The project shows basic procedural compliance: a VVB (CTI) confirmed additionality and an operational monitoring period and smart meter monitoring are documented. However, key gaps and contradictions remain (notably on leakage treatment, benefit sharing, and crediting period), and several corrective actions were raised and closed, reducing confidence in robustness.

Project Description

Developer: Climate Bridge (Shanghai) Ltd. Type: Solar Thermal - Electricity Size: Small Scale Methodology: AMS-I.D. Grid connected renewable electricity generation Crediting period: 2013-12-08 → 2027-12-07 Estimated annual credits: 11253 tCO2e SDGs: Goal 13: Climate Action, Goal 7: Affordable and Clean Energy, Goal 8: Decent Work and Economic Growth

Red Flags

  • Leakage justification is not addressed in the latest documents despite a 0% leakage deduction.
  • Contradictory records on additionality test type, benefit sharing, and crediting period across documents reduce data reliability.

Credit Vintages

Issued Retired Available
2013
304 304 0
2014
12,070 12,070 0
2015
2,956 2,956 0
2019
4,105 82 4,023
2020
10,899 217 10,682
Total 30,334 15,629 14,705

Cosa migliorerebbe questo punteggio

  • Provide explicit leakage justification or a quantified leakage assessment and support for the 0% deduction in project documents.
  • Publish or link clear evidence documents (full verification/monitoring reports) and the verified emissions figures so total reductions verified are transparent.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed

Permanence

no buffer info

Leakage

justification missing

Baseline

project-specific baseline

Safeguards

FPIC & grievance present

Double-claim

CORSIA/CCP status unclear

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-24 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti