Audit Analysis
A Gold Standard fuel-wood stove project in Nigeria with VVB-confirmed additionality and quantified leakage, but hampered by a project-specific baseline, no stated buffer pool, an 8.35% user drop-out rate, and significant operational disruption from Boko Haram conflict. The project delivered roughly 9.5× the pro-rata ex-ante expectation for the short monitoring period, indicating very conservative crediting, yet deployed only 35% of the planned stoves. Multiple contradictions across documents and a self-report monitoring method temper confidence in the data.
Red Flags
- Stove deployment fell to 4,370 units versus 12,500 planned (35% of target), driven by Boko Haram conflict and political instability, raising questions about the robustness of the ex-ante activity assumptions.
- An 8.35% user drop-out rate was recorded in MP8, and no new cooking demonstrations were conducted during the latest monitoring period, indicating weakening user engagement and potential reversion to traditional cooking.
- No buffer pool percentage is stated in any available document, leaving permanence risk for an energy-efficiency project (stove breakage, user reversion) unquantified.
- Usage monitoring relies on self-reporting per the 2020 verification report, a method with lower data reliability than the annual survey referenced in the 2018 report.
- Six contradictions were identified across documents, including conflicting crediting-period start dates, divergent ERR figures, and inconsistent leakage justifications, reducing overall data reliability.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 376 | 0 | 376 | |
| 2010 | 4,645 | 0 | 4,645 | |
| 2011 | 8,679 | 0 | 8,679 | |
| 2012 | 9,611 | 0 | 9,611 | |
| 2013 | 8,908 | 0 | 8,908 | |
| 2014 | 10,264 | 0 | 10,264 | |
| 2015 | 11,355 | 0 | 11,355 | |
| 2016 | 12,174 | 0 | 12,174 | |
| 2017 | 12,143 | 0 | 12,143 | |
| 2018 | 11,029 | 0 | 11,029 | |
| 2019 | 8,113 | 0 | 8,113 | |
| Total | 97,297 | 0 | 97,297 |
Risk Indicators
VVB-confirmed combined test
No buffer pool stated; 8.35% drop-out
1% quantified deduction
Project-specific; reassessment timing not stated
FPIC, grievance mechanism, safeguards documented
CORSIA and CCP status not stated
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →