*Energeticos Jaremar - Biogas recovery from Palm Oil Mill Effluent (POME) ponds, and heat & electricity generation, Honduras
GS-837 ↗ · current registry ID: GS470
#43of 111 in Biogas#277of 426 in Gold Standard (GS)#18of 42 in AMS-I.C
Audit Analysis
A CDM biogas cogeneration project in Honduras with VVB-confirmed additionality (barrier test) and a reputable verifier (TÜV NORD CERT), but undermined by a project-specific baseline, a 0% leakage deduction justified only as 'deemed negligible,' and seven corrective action requests plus one finding of non-conformity raised during verification. Multiple data-quality issues and gaps in the extracted record (no verified ERR figure, no FNRB, no LCA) limit confidence in the claimed credits.
Red Flags
- Seven corrective action requests (CAR A2, A3, B2, D2, D3, D5, D6) and one finding of non-conformity (FAR 1) were raised in the verification report, indicating significant data-quality and compliance issues during the monitoring period.
- Leakage deduction is 0% with only a 'deemed negligible' justification; no quantitative analysis or sensitivity test is documented for a project where displaced biogas could be flared or captured by a third party.
- The grid emission factor of 646 gCO2/kWh is anchored to 2006 data; no updated or reassessed baseline emission factor is found in the extracted record.
- The monitoring plan revision was still ongoing at the time of the 2014 verification report, as requested by the UNFCCC Executive Board during the first project verification.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2008 | 33,331 | 0 | 33,331 | |
| 2009 | 51,491 | 0 | 51,491 | |
| 2010 | 45,188 | 0 | 45,188 | |
| 2011 | 58,417 | 0 | 58,417 | |
| 2012 | 66,855 | 0 | 66,855 | |
| Total | 255,282 | 0 | 255,282 |
Risk Indicators
VVB-confirmed barrier test
No reversal events stated; no buffer pool documented
0% deduction, 'deemed negligible' only
Project-specific; no reassessment date found
Safeguards mentioned; FPIC and grievance mechanism not state
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →