*Energeticos Jaremar - Biogas recovery from Palm Oil Mill Effluent (POME) ponds, and heat & electricity generation, Honduras

GS-837 ↗ · current registry ID: GS470

#43of 111 in Biogas#277of 426 in Gold Standard (GS)#18of 42 in AMS-I.C

4.9/ 10
Integrity
5.2
Transparency
4.8
Claim Safety
4.8
Documentation
4.3

Audit Analysis

A CDM biogas cogeneration project in Honduras with VVB-confirmed additionality (barrier test) and a reputable verifier (TÜV NORD CERT), but undermined by a project-specific baseline, a 0% leakage deduction justified only as 'deemed negligible,' and seven corrective action requests plus one finding of non-conformity raised during verification. Multiple data-quality issues and gaps in the extracted record (no verified ERR figure, no FNRB, no LCA) limit confidence in the claimed credits.

Red Flags

  • Seven corrective action requests (CAR A2, A3, B2, D2, D3, D5, D6) and one finding of non-conformity (FAR 1) were raised in the verification report, indicating significant data-quality and compliance issues during the monitoring period.
  • Leakage deduction is 0% with only a 'deemed negligible' justification; no quantitative analysis or sensitivity test is documented for a project where displaced biogas could be flared or captured by a third party.
  • The grid emission factor of 646 gCO2/kWh is anchored to 2006 data; no updated or reassessed baseline emission factor is found in the extracted record.
  • The monitoring plan revision was still ongoing at the time of the 2014 verification report, as requested by the UNFCCC Executive Board during the first project verification.

Credit Vintages

IssuedRetiredAvailable
2008
33,331033,331
2009
51,491051,491
2010
45,188045,188
2011
58,417058,417
2012
66,855066,855
Total255,2820255,282

Risk Indicators

Additionality

VVB-confirmed barrier test

Permanence

No reversal events stated; no buffer pool documented

Leakage

0% deduction, 'deemed negligible' only

Baseline

Project-specific; no reassessment date found

Safeguards

Safeguards mentioned; FPIC and grievance mechanism not state

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-24AMS-I.C. ver. 11

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents