GS1247 VPA 75 Lango Safe Water Project
GS-919 ↗ · current registry ID: GS5189
#1011of 1329 in Industrial#129of 163 in Uganda#1444of 1801 in Gold Standard (GS)
Audit Analysis
The Lango Safe Water Project is a long-running Gold Standard water-pumping efficiency project in Uganda with a confirmed additionality test and no reversal events, but it is burdened by an unusually high volume of material findings, 22 corrective actions, and ten cross-document contradictions that significantly undermine confidence in the underlying data. The leakage treatment is internally inconsistent (0% deduction in the verification report versus 5% in the PDD, with conflicting justifications), and the fNRB calculation was flagged for using an incorrect tool version. Overall, the project's design logic is sound but the data quality and documentation consistency are well below the level expected for a mature, multi-year project.
Red Flags
- Ten cross-document contradictions identified, including a 13.6× discrepancy in claimed ER between the PDD (4,403) and the monitoring report (60,139), and conflicting leakage treatments (0% vs 5% deduction with opposing justifications).
- 22 corrective actions required, including recalculation of the fNRB using the correct Tool 30 version, correction of non-functional day counts for multiple boreholes, and provision of missing GPS coordinates — indicating systemic data-quality weaknesses.
- Leakage deduction of 0% in the verification report contradicts the 5% deduction in the PDD, and the justification shifts between 'quantified' and 'deemed negligible' across documents, leaving the true leakage treatment unclear.
- Grievance mechanism books were being used as guest books by water guardians, indicating the safeguard was not functioning as intended at the community level.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2017 | 8,290 | 8,290 | 0 | |
| 2018 | 10,000 | 10,000 | 0 | |
| 2019 | 5,393 | 5,393 | 0 | |
| 2020 | 3,538 | 2,027 | 1,511 | |
| 2021 | 1,901 | 1,607 | 294 | |
| 2022 | 2,139 | 2,097 | 42 | |
| 2023 | 511 | 0 | 511 | |
| Total | 31,772 | 29,414 | 2,358 |
Risk Indicators
VVB-confirmed combined test
mixed evidence / unresolved risk
0% deduction contradicts PDD 5%; justification inconsistent
Project-specific baseline, reassessed 2024
FPIC done; grievance mechanism present but misused in practice
CORSIA and CCP status both unknown
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →