Kuyucak 25.6 MW Wind Farm Project, Turkey

GS-1009 ↗

5.0 / 10
Integrity
6.1
Transparency
4.8
Claim Safety
4.6
Documentation
3.7

Score Breakdown

Integrity

verified Additionality was confirmed by the VVB using an investment test in the verification report.

missing The verification report lists multiple corrective actions, and the monitoring period was noted as inconsistent with the ER calculation spreadsheet.

Transparency

verified The monitoring report uses smart meters and the verification report names KBS Certification Services Ltd. as the VVB.

missing Low extraction confidence, conflicting verified emissions figures, and a disputed crediting period reduce confidence in the public record.

Claim Safety

verified The project is a wind farm with a project baseline and no leakage deduction, which is generally straightforward for this sector.

missing The verified emissions reductions differ sharply across documents, and the project is CORSIA-eligible while CCP status is not mentioned.

Documentation

verified A relatively large document set was used, and the verification report is recent.

missing Extraction confidence is low, and the record contains several unresolved contradictions plus multiple corrective actions.

Detailed Analysis

Integrity

The verification report confirms additionality through an investment test and says the VVB closed out the reported corrective actions before issuance. The project also shows a leakage deduction of 0% with leakage described as negligible, and no reversal events are reported in the extracted record. That said, the report also notes that the monitoring period was not consistent with the ER calculation spreadsheet, which weakens confidence in the underlying accounting.

Transparency

The monitoring report covers 2024-03-01 to 2024-11-10 and the verification report identifies KBS Certification Services Ltd. as the VVB, with smart-meter monitoring described. Still, the extraction confidence is low, and the record contains a major discrepancy in verified emissions reductions between 63,654 and 142,169. The crediting period also conflicts across documents, which reduces transparency and auditability.

Claim Safety

For a wind project, the project baseline and negligible leakage treatment are broadly supportive of claim safety. However, the large gap between claimed and verified emissions reductions, together with the conflicting verified totals across documents, raises over-crediting risk. The project is marked CORSIA-eligible, while CCP status is not mentioned, so dual-claim exposure cannot be ruled out from the extracted record.

Documentation

The record draws on many documents, and the verification report is dated 2025-07-25, which is reasonably recent. Even so, the extraction confidence is low, and several material findings and corrective actions were raised. The contradictions around emissions reductions, leakage treatment, benefit sharing, and the crediting period indicate incomplete or inconsistent documentation.

Overall

The project looks stronger on core project logic than on record reliability: additionality is VVB-confirmed and leakage appears negligible, but the documentation is inconsistent. I privileged the 2025-07-25 verification report for the latest values on leakage, additionality framing, and the current crediting period because it is the most recent and specific source, while noting that earlier documents conflict on leakage, additionality test type, CCP status, benefit sharing, emissions reductions, and crediting period. Those contradictions materially reduce confidence, and the low extraction confidence plus unresolved corrective-action history keep the overall score moderate rather than high.

Audit Analysis

This is a wind project with a VVB-confirmed investment additionality test, no leakage deduction, and no reported reversal events in the extracted record. However, the evidence set has reliability issues: the extraction confidence is low, several corrective actions were raised, and key figures such as verified emissions reductions and the crediting period conflict across documents.

Project Description

Developer: Alize Enerji Elektrik Uretim Anonim Sirketi Type: Wind Size: Large Scale Methodology: ACM0002 Grid-connected electricity generation from renewable sources Crediting period: 2010-11-11 → 2031-11-10 Estimated annual credits: 71578 tCO2e SDGs: Goal 13: Climate Action, Goal 7: Affordable and Clean Energy, Goal 8: Decent Work and Economic Growth

Red Flags

  • The verified emissions reductions conflict across documents, with one report showing 63,654 and an earlier document showing 142,169.
  • The crediting period also conflicts, and the monitoring period was flagged as inconsistent with the ER calculation spreadsheet.
  • Leakage treatment changed across documents, with one source describing leakage as quantified and the later verification report treating it as negligible.
  • The project is CORSIA-eligible, which keeps dual-claim risk relevant even though CCP approval is not mentioned.

Credit Vintages

Issued Retired Available
2010
2,386 2,386 0
2011
45,607 45,607 0
2012
46,893 46,893 0
2013
44,617 44,617 0
2014
9,142 9,142 0
2022
10,241 0 10,241
2023
44,022 0 44,022
2024
43,516 0 43,516
Total 246,424 148,645 97,779

Cosa migliorerebbe questo punteggio

  • Provide a reconciled emissions-reduction schedule that explains the difference between the 63,654 and 142,169 verified figures.
  • Publish a document-controlled reconciliation of the crediting period, leakage treatment, and monitoring-period spreadsheet so the latest verification report can be independently traced.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

No reversal events reported, but not fully addressed

Leakage

Negligible leakage claimed, but prior quantified treatment c

Baseline

Project baseline stated, reassessment timing not fully robus

Safeguards

FPIC and grievance mechanism documented

Double-claim

CORSIA-eligible; CCP status not mentioned

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-19 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti