Score Breakdown
Integrity
verified The issuance report from 2023 shows additionality was confirmed by the VVB, and no material findings or corrective actions were reported.
missing Leakage deduction is not stated in the extracted record, buffer pool coverage is not found, and the contradiction on leakage treatment creates uncertainty.
Transparency
verified The project has a named VVB and a long monitoring period ending in 2017, with a quantified verified issuance total of 1,069,816 credits.
missing Total claimed issuance is not found, usage monitoring is not described, and the extraction confidence is only medium with one evidence document listed as unknown.
Claim Safety
verified The project is not CORSIA-eligible, which reduces dual-market claim risk, and the baseline was reassessed in 2020.
missing The baseline is project-specific rather than clearly standardized, and leakage justification is mixed because one document says negligible while another says it was quantified.
Documentation
verified Eighteen documents were used, and the issuance record is relatively recent, dated 2023.
missing Several key fields are not stated in available documents, and the contradictions across older and newer documents indicate uneven documentation quality.
Detailed Analysis
Integrity
The issuance report dated 2023 shows additionality was confirmed by the VVB, and it reports no material findings or corrective actions. However, leakage deduction is not stated in the extracted record and buffer pool coverage is not found, which weakens permanence and leakage confidence. The project is a biomass power project, so these missing elements matter for overall integrity.
Transparency
The record identifies the VVB and provides a verified issuance total of 1,069,816 credits over the monitoring period from 2009-09-10 to 2017-09-23. But total claimed issuance is not found, usage monitoring is not described, and the extracted evidence list is sparse. Medium extraction confidence also suggests at least one key document was not fully readable.
Claim Safety
Claim safety is helped by the fact that the project is not CORSIA-eligible, which lowers dual-claim exposure. Still, the baseline is project-specific rather than clearly standardized, and the leakage story is inconsistent: the latest record says leakage was deemed negligible, while an earlier document says it was quantified. That inconsistency raises over-crediting and claim-quality risk.
Documentation
Documentation is moderate rather than strong: 18 documents were used and the issuance record is recent, but several important fields are not stated in available documents. The contradictions on FPIC, safeguards, grievance mechanism, benefit sharing, additionality test type, leakage treatment, and crediting period show that the record is not fully internally consistent. The medium extraction confidence further lowers confidence in completeness.
Overall
I privileged the 2023 issuance record for the final values because it is the most recent and authoritative document in the set, but I reduced confidence because the contradictions show earlier documents disagree on several material points. In particular, I treated the later leakage characterization as controlling, while noting that an earlier document reported quantified leakage; I also privileged the later statements that FPIC, safeguards, grievance mechanism, and benefit sharing were present. Because the project is registered and has VVB-confirmed additionality, the score is not weak, but missing leakage/buffer details and the contradictory record prevent a higher rating.
Audit Analysis
This is a registered VCS biomass project with VVB-confirmed additionality and no material findings reported in the issuance record. The main weaknesses are documentation gaps around leakage quantification, buffer pool treatment, and usage monitoring, plus several contradictions across source documents that reduce confidence in the record.
Project Description
The Liucheng Biomass Power Generation Project in Guangxi Zhuang Autonomous Region, China uses discarded mulberry and sugarcane leaves to construct a biomass residues power generation plant. The project is operated by Liuzhou City Xin'neng Biomass Power Generation Co., Ltd. and will use 178,198 tons of biomass residues.
Red Flags
- Leakage treatment is inconsistent across documents: one source says leakage was deemed negligible, while an earlier document indicates it was quantified.
- The record contains contradictions on FPIC, safeguards, grievance mechanism, benefit sharing, additionality test type, and crediting period, which weakens reliability.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 36,996 | 36,996 | 0 | |
| 2010 | 123,279 | 116,547 | 6,732 | |
| 2011 | 112,560 | 63,257 | 49,303 | |
| 2012 | 112,807 | 65,981 | 46,826 | |
| 2013 | 125,876 | 117,624 | 8,252 | |
| 2014 | 165,752 | 165,752 | 0 | |
| 2015 | 143,247 | 142,349 | 898 | |
| 2016 | 147,474 | 29,571 | 117,903 | |
| 2017 | 115,077 | 107,324 | 7,753 | |
| Total | 1,083,068 | 845,401 | 237,667 |
Cosa migliorerebbe questo punteggio
- Publish a clear leakage assessment with the final deduction method and reconcile the conflicting leakage statements across documents.
- Provide a complete monitoring package showing usage monitoring, claimed versus verified issuance, and explicit buffer pool or reversal treatment.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed additionality
No buffer pool stated
Leakage treatment inconsistent
Project baseline with reassessment
FPIC and grievance mechanism documented
Not CORSIA-eligible
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →