Parbati Hydroelectric Project Stage III
#1531of 1935 in Renewable energy#847of 975 in India#1109of 1339 in Verra (VCS)#1168of 1287 in ACM0002
Audit Analysis
The Parbati Hydroelectric Stage III project uses a well-established methodology (ACM0002 v16) with a jurisdictional baseline and VVB-confirmed additionality, but is severely undermined by over 40 material findings, 24 corrective actions, and major inconsistencies in reported emission reductions across verification and monitoring documents. The project over-delivered relative to its pro-rata ex-ante expectation (~209%), which is positive for claim safety, yet the data reliability issues and gaps in leakage justification, FNRB, and usage monitoring limit confidence in the overall credit quality.
Red Flags
- Over 40 material findings and 24 corrective actions identified across verification and validation reports, including inconsistent GHG emission reductions between the VR, MR, and ER calculation sheet
- Verified ERR of 708,572 tCO₂e (VR, Oct 2024) is 81% lower than the 3,791,042 tCO₂e verified in the earlier VR (Jan 2024) for what appears to be the same monitoring period, indicating a serious data reliability problem
- The common practice additionality analysis was found to use an inappropriate temporal constraint (Kyoto Protocol ratification date) and required re-conducting, with discrepancies in IRR and geographical scope
- Leakage deduction of 0% with justification recorded as 'not addressed' in the most recent verification report, despite the project type (hydroelectric) where displacement effects should be explicitly considered
- Missing generation data records for specific dates in 2015, 2017, 2018, and 2020, and delayed meter calibration (export meters from March 2021 to June 2022; import meters from April 2022 to June 2022) with a 100% error factor applied
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 630,977 | 530,214 | 100,763 | |
| Total | 630,977 | 530,214 | 100,763 |
Risk Indicators
Verified but required re-conduct
Hydro project – no reversal risk
0% deduction, justification not addressed
Jurisdictional, reassessment timing unclear
Present per 2024 VR, gaps in 2023 VR
CORSIA excluded, CCP status unknown
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →