Vai al contenuto principale
VCS Energy industries (renewable/non-renewable sources) India Registry: Registered Documentazione completa General Methodology v2.0

Renewable Power Project by Devarahipparigi Wind Power Private Limited

VCS-1793 ↗

4.8 / 10
Integrity
4.8
Transparency
4.9
Claim Safety
5.2
Documentation
4.1

Score Breakdown

Integrity

verified Additionality was confirmed by the VVB in the verification report, which supports the project’s core eligibility claim.

missing The verification report lists multiple findings and corrective actions, including a mismatch between the emission reduction formula and the applied methodology, which weakens confidence in the quantified reductions.

Transparency

verified The monitoring period and verified emission total are stated in the verification report, and the project is clearly identified under VCS with a named VVB.

missing Key transparency items are not stated in the extracted record, including the usage monitoring method, leakage deduction, and baseline reassessment timing; extraction confidence is also low.

Claim Safety

verified The project is not CORSIA-eligible, which reduces dual-market claim risk on that channel.

missing The baseline is project-specific rather than a standardized or jurisdictional baseline, and the large discrepancy in verified ERs across documents raises over-crediting risk.

Documentation

verified The record includes a substantial set of extracted facts from official documents, including a verification report dated 2024-01-19 and 22 documents used.

missing Extraction confidence is low, and several important fields are missing or not stated, which limits documentation reliability and completeness.

Detailed Analysis

Integrity

The verification report confirms additionality through VVB review, which is a meaningful positive for integrity. However, the report also lists 10 findings, including 06 CARs, 03 CLs, and 01 FAR, and specifically notes that the net emission reduction formula was not in line with the applied methodology. Reversal risk is not well addressed because reversal events are marked as not addressed and no buffer pool percentage is available.

Transparency

The project has a named verifier, a defined monitoring period from 2021-01-01 to 2022-12-31, and a verified total of 476,001 ERs in the verification report. Still, several transparency-critical items are not stated in the extracted record, including the usage monitoring method, baseline reassessment timing, and leakage deduction. The low extraction confidence further reduces trust in the completeness of the documentation.

Claim Safety

Claim safety is helped by the fact that the project is not CORSIA-eligible, lowering one channel of dual-claim risk. But the baseline is project-specific, leakage treatment is only described as deemed negligible without a quantified deduction, and the verification report notes that actual emission reductions were 9.9% higher than the registered PDD estimate for the comparable period. The large discrepancy between the later verified ER total and the earlier figure in the contradictions list also raises over-crediting concerns.

Documentation

The evidence set is reasonably broad, with 22 documents used and a recent verification report dated 2024-01-19. Even so, the extraction confidence is low, and multiple important fields are missing or only partially described, such as the usage monitoring method and baseline reassessment. The presence of several corrective actions and a FAR also indicates that the documentation package was not clean or fully settled.

Overall

Overall, this is a moderately credible renewable energy crediting case, but the score is held back by documentation weaknesses and reliability concerns in the quantified reductions. I privileged the 2024-01-19 verification report for the latest verified ER figure because it is the most recent official record, but I discounted confidence because the contradictions list shows an earlier verified total of 268,604 and the report itself contains multiple findings and methodology concerns. The leakage contradiction was resolved in favor of the later report’s deemed-negligible treatment, while the earlier record suggesting leakage was not addressed lowers confidence rather than being ignored.

Audit Analysis

This is a registered wind project with VVB-confirmed additionality and no reported reversal events, but the evidence package has notable quality issues. The verification report raised 10 findings, including CARs and a FAR, and the reported emission reductions differ materially from an earlier verification record, which weakens confidence in the claim.

Project Description

Proponent: Devarahipparigi Wind Power Private Limited Protocol categories: Energy industries (renewable/non-renewable sources) Protocols: ACM0002 Estimated annual GHG reductions: 195052 tCO2e Region: Asia Registration date: 2018-12-10

Red Flags

  • The verification report raised 10 findings, including 06 CARs, 03 CLs, and 01 FAR, with unresolved wording around stakeholder communication and calculation consistency.
  • A later verification record reports 476,001 verified ERs, while an earlier record in the contradictions list shows 268,604, indicating a large cross-document inconsistency.

Credit Vintages

Issued Retired Available
2017
191,352 191,352 0
2018
269,033 189,252 79,781
2019
297,525 202,279 95,246
2020
452,144 22,752 429,392
2021
241,925 23,000 218,925
2022
234,076 0 234,076
Total 1,686,055 628,635 1,057,420

Cosa migliorerebbe questo punteggio

  • Provide a clean, reconciled emissions calculation trail that explains the 9.9% difference versus the registered PDD estimate and resolves the earlier verified ER discrepancy.
  • Disclose the baseline reassessment history, leakage treatment, and any buffer or reversal provisions in a single consistent monitoring package.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed additionality

Permanence

No buffer pool stated

Leakage

Negligible but not quantified

Baseline

Project baseline, reassessment missing

Safeguards

FPIC and grievance mechanism present

Double-claim

Not CORSIA-eligible; CCP not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-19 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti