Audit Analysis
The UpEnergy cooking-device project in Uganda has VVB-confirmed additionality and no reported reversal events, but suffers from a project-specific baseline, an unaddressed 0% leakage deduction, and a large number of corrective actions (22 items) spanning typos and substantive parameter inconsistencies. ERR delivery appears reasonable (verified 7,601 vs. claimed 7,732), though the absence of a lifetime ex-ante figure and multiple cross-document contradictions limit confidence in the credit quantity.
Red Flags
- Leakage deduction is 0% with justification recorded as 'not addressed' in the verification report, while the monitoring report claims it was 'quantified' — a direct contradiction that leaves the leakage treatment unresolved for a project displacing solid-fuel cooking.
- 22 corrective actions were required by the VVB, including substantive issues such as inconsistent emission-reduction caps, wrong-version stakeholder consultation reports, and baseline emission-factor equation errors, indicating weak internal quality control.
- FPIC status is contradictory: the verification report (Oct 2024) states it was not conducted, while the validation report (Dec 2025) states it was — the more recent validation report's date is anomalous and the discrepancy is unresolved.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2022 | 1,082 | 0 | 1,082 | |
| 2023 | 6,650 | 0 | 6,650 | |
| Total | 7,732 | 0 | 7,732 |
Risk Indicators
VVB-confirmed combined test
no reversals
0% deduction, justification not addressed
Project-specific; reassessment date not stated
Grievance mechanism present; FPIC contradictory
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →