AMS-III.Z — Fuel Switch, process improvement and energy efficiency in brick manufacture

About this methodology

Projects improve brickmaking processes or change to lower-emission fuels. The method measures reductions from using less energy or less carbon-intensive energy for brick production.

Version
6.0 · source ·
Status
Active at CDM / UNFCCC · source ·
Climate outcome
Emission reductions
Activity
Bricks
Official page
cdm.unfccc.int ·
Also used by projects of
2 more

How methodology v3 reads projects of this type

What CarbonMeld reads

  • shown

    Grid emission factor: the methodology sets rules for it in some cases. CarbonMeld reads it in the project's documents. CM-F-AMS-III-Z-GRID-EF

    Link
  • shown

    Leakage: the methodology sets rules for it in some cases (AMS-III.Z v06, p. 10). CarbonMeld reads it in the project's documents. CM-F-AMS-III-Z-LEAKAGE

    Link
  • shown

    Fraction of non-renewable biomass (fNRB): the methodology sets rules for it in some cases (AMS-III.Z v06, p. 6). CarbonMeld reads it in the project's documents. CM-F-AMS-III-Z-FNRB

    Link
  • A confirmed investment analysis A-INVEST

    The documents show a project-level additionality test, the validation confirmed it, and it is an investment analysis (a numeric test of the project's finances with and without carbon revenue).

Figures set against the methodology's own values

  • Integrity comparison

    The small-scale limit is 60 kt CO2e per year (p. 5). CarbonMeld compares the project's annual estimate with it. CM-F-AMS-III-Z-SMALL-SCALE-LIMIT

    small-scale limit: 60 kt CO2e per year

    Link
  • fNRB above the official value, or an older default Q-FNRB-ABOVE

    CarbonMeld compares the fraction of non-renewable biomass (fNRB) with the official national value of the country. The rule applies to any project whose documents give an fNRB that CarbonMeld can compare with the official value. A project gets one fNRB deduction at most. Three sources of values get no deduction: TOOL33 version 03.0, A6.4-AMT-009, and a MoFuSS assessment whose stated year is 2024 or later.

    Above the official national value plus its 30% uncertainty.

Deductions that can apply

  • fNRB above the official value, or an older default Q-FNRB-OLD-DEFAULT

    CarbonMeld compares the fraction of non-renewable biomass (fNRB) with the official national value of the country. The rule applies to any project whose documents give an fNRB that CarbonMeld can compare with the official value. A project gets one fNRB deduction at most. Three sources of values get no deduction: TOOL33 version 03.0, A6.4-AMT-009, and a MoFuSS assessment whose stated year is 2024 or later.

    An older default value. This includes the TOOL33 values before version 03.0, the older national defaults and MoFuSS values whose stated year is before 2024. It also includes any other value that the documents give as a default. The CDM's fixed default of 0.3 is the exception. Only the two «above» cases can apply to it.

Set by the methodology or the programme, not assessed by our current method

  • not assessed

    No legal requirement for the activity: the methodology sets rules for it (AMS-III.Z v06 para 12, p. 6). Our current method does not assess it. CM-F-AMS-III-Z-REGULATORY-SURPLUS

    Link
  • not assessed

    Social safeguards and consent of communities (FPIC): any such rules come from the programme, not the methodology. Our current method does not assess it. CM-F-AMS-III-Z-SAFEGUARDS-FPIC

    Link

Not applicable to this type — never a gap in our current method

The criterion does not apply to this methodology. Our current method never counts it as a gap.

The general rules apply as well. Read the general rules.

The rules of methodology v2.2, as they were: the archived v2.2 page.

History and transitions

All 6 versions
  • v06.0adopted 24 Jul 2015source

    Include non-renewable biomass as the eligible baseline fuel type by referring to the approved methodology AMS-II.G, which provide detailed guidance on the demonstration of renewability of the biomass and its emission factor.

  • v05.0adopted 1 Jun 2014source

    To include the criteria for debundling check as per EB 77 mandate, and include a reference to tool “Project emissions from cultivation of biomass”.

  • v04.0adopted 11 May 2012source

    To expand its applicability for a complete switch from fossil fuel to renewable biomass and provide further guidelines to determine baseline emissions for Greenfield and capacity-addition project activity.

  • v03.0adopted 28 May 2010source

    To include project activities involving complete/partial substitution of high carbon fossil fuels with low carbon fossil fuels.

  • v02.0adopted 28 May 2009source

    To simplify the requirements to establish the comparability level of service (e.g. comparability of compressive strength) of baseline bricks and the project bricks.

  • v01.0adopted 25 Mar 2009source

    Initial adoption.

Projects using AMS-III.Z

Browse 57 published projects using AMS-III.Z, listed alphabetically. There is no ranking for this methodology yet: it appears here automatically once 5 of its projects not in the pipeline or under validation are rated. Open a project to view its registry details and the analysis available for that project.

Which registries list projects under AMS-III.Z?

In CarbonMeld's data, AMS-III.Z projects are on 6 registries: CDM (31), Verra (16) and Gold Standard (6), and 3 more. Being listed on a registry is not the same as being registered: the «Registered» column counts the projects each registry shows as registered, and credits are issued only after each verification.

RegistryProjectsRegisteredProjects list
CDM (UNFCCC)3113See the list
Verra (VCS)164See the list
Gold Standard (GS)64See the list
Universal Carbon Registry (UCR)22See the list
Global Carbon Council (GCC)10See the list
International Carbon Registry (ICR)10See the list

Counts of project records in CarbonMeld's data, with or without a CarbonMeld analysis. «Registered» counts the records whose current registry status is «registered», as last read (24 November 2026); projects in a later status, such as awaiting verification approval, late to verify or completed, are not in that column.

12 of these projects have no number: additionality, quantification or both have no public grade of their type of project that applies to them yet. Their pages give the reason and how many negative facts were found; the analysis is in Premium.

← All leaderboards · Full database