Grid emission factor: the methodology sets rules for it in some cases. CarbonMeld reads it in the project's documents. CM-F-AMS-III-Z-GRID-EF
AMS-III.Z — Fuel Switch, process improvement and energy efficiency in brick manufacture
About this methodology
Projects improve brickmaking processes or change to lower-emission fuels. The method measures reductions from using less energy or less carbon-intensive energy for brick production.
- Issued by
- CDM (UNFCCC) · issuer's site
- Version
- 6.0 · source ·
- Status
- Active at CDM / UNFCCC · source ·
- Climate outcome
- Emission reductions
- Activity
- Bricks
- Official page
- cdm.unfccc.int ·
- Also used by projects of
- Verra (VCS) (16 projects)
- Gold Standard (GS) (6 projects)
- Universal Carbon Registry (UCR) (2 projects)
2 more
- Global Carbon Council (GCC) (1 project)
- International Carbon Registry (ICR) (1 project)
How methodology v3 reads projects of this type
What CarbonMeld reads
- shown
- shown
Leakage: the methodology sets rules for it in some cases (AMS-III.Z v06, p. 10). CarbonMeld reads it in the project's documents. CM-F-AMS-III-Z-LEAKAGE
- shown
Fraction of non-renewable biomass (fNRB): the methodology sets rules for it in some cases (AMS-III.Z v06, p. 6). CarbonMeld reads it in the project's documents. CM-F-AMS-III-Z-FNRB
A confirmed investment analysis A-INVEST
The documents show a project-level additionality test, the validation confirmed it, and it is an investment analysis (a numeric test of the project's finances with and without carbon revenue).
Figures set against the methodology's own values
- Integrity comparison
The small-scale limit is 60 kt CO2e per year (p. 5). CarbonMeld compares the project's annual estimate with it. CM-F-AMS-III-Z-SMALL-SCALE-LIMIT
small-scale limit: 60 kt CO2e per year
fNRB above the official value, or an older default Q-FNRB-ABOVE
CarbonMeld compares the fraction of non-renewable biomass (fNRB) with the official national value of the country. The rule applies to any project whose documents give an fNRB that CarbonMeld can compare with the official value. A project gets one fNRB deduction at most. Three sources of values get no deduction: TOOL33 version 03.0, A6.4-AMT-009, and a MoFuSS assessment whose stated year is 2024 or later.
Above the official national value plus its 30% uncertainty.
Deductions that can apply
fNRB above the official value, or an older default Q-FNRB-OLD-DEFAULT
CarbonMeld compares the fraction of non-renewable biomass (fNRB) with the official national value of the country. The rule applies to any project whose documents give an fNRB that CarbonMeld can compare with the official value. A project gets one fNRB deduction at most. Three sources of values get no deduction: TOOL33 version 03.0, A6.4-AMT-009, and a MoFuSS assessment whose stated year is 2024 or later.
An older default value. This includes the TOOL33 values before version 03.0, the older national defaults and MoFuSS values whose stated year is before 2024. It also includes any other value that the documents give as a default. The CDM's fixed default of 0.3 is the exception. Only the two «above» cases can apply to it.
Set by the methodology or the programme, not assessed by our current method
- not assessed
No legal requirement for the activity: the methodology sets rules for it (AMS-III.Z v06 para 12, p. 6). Our current method does not assess it. CM-F-AMS-III-Z-REGULATORY-SURPLUS
- not assessed
Sustainability of the feedstock: the methodology sets rules for it in some cases. Our current method does not assess it. CM-F-AMS-III-Z-FEEDSTOCK-SUSTAINABILITY
- not assessed
Social safeguards and consent of communities (FPIC): any such rules come from the programme, not the methodology. Our current method does not assess it. CM-F-AMS-III-Z-SAFEGUARDS-FPIC
Not applicable to this type — never a gap in our current method
The criterion does not apply to this methodology. Our current method never counts it as a gap.
- CM-N-BUFFERBuffer pool
- CM-N-PERMANENCE-REVERSALPermanence and reversals
- CM-N-USAGEUsage rate of the devices
- CM-N-DURABILITY-MEASUREMENTDurability of the storage
- CM-N-END-USE-TRACKINGTracking of the end use
The general rules apply as well. Read the general rules.
The rules of methodology v2.2, as they were: the archived v2.2 page.
History and transitions
All 6 versions
-
v06.0adopted 24 Jul 2015source
Include non-renewable biomass as the eligible baseline fuel type by referring to the approved methodology AMS-II.G, which provide detailed guidance on the demonstration of renewability of the biomass and its emission factor.
-
v05.0adopted 1 Jun 2014source
To include the criteria for debundling check as per EB 77 mandate, and include a reference to tool “Project emissions from cultivation of biomass”.
-
v04.0adopted 11 May 2012source
To expand its applicability for a complete switch from fossil fuel to renewable biomass and provide further guidelines to determine baseline emissions for Greenfield and capacity-addition project activity.
-
v03.0adopted 28 May 2010source
To include project activities involving complete/partial substitution of high carbon fossil fuels with low carbon fossil fuels.
-
v02.0adopted 28 May 2009source
To simplify the requirements to establish the comparability level of service (e.g. comparability of compressive strength) of baseline bricks and the project bricks.
-
v01.0adopted 25 Mar 2009source
Initial adoption.
Projects using AMS-III.Z
Browse 57 published projects using AMS-III.Z, listed alphabetically. There is no ranking for this methodology yet: it appears here automatically once 5 of its projects not in the pipeline or under validation are rated. Open a project to view its registry details and the analysis available for that project.
Which registries list projects under AMS-III.Z?
In CarbonMeld's data, AMS-III.Z projects are on 6 registries: CDM (31), Verra (16) and Gold Standard (6), and 3 more. Being listed on a registry is not the same as being registered: the «Registered» column counts the projects each registry shows as registered, and credits are issued only after each verification.
| Registry | Projects | Registered | Projects list |
|---|---|---|---|
| CDM (UNFCCC) | 31 | 13 | See the list |
| Verra (VCS) | 16 | 4 | See the list |
| Gold Standard (GS) | 6 | 4 | See the list |
| Universal Carbon Registry (UCR) | 2 | 2 | See the list |
| Global Carbon Council (GCC) | 1 | 0 | See the list |
| International Carbon Registry (ICR) | 1 | 0 | See the list |
Counts of project records in CarbonMeld's data, with or without a CarbonMeld analysis. «Registered» counts the records whose current registry status is «registered», as last read (24 November 2026); projects in a later status, such as awaiting verification approval, late to verify or completed, are not in that column.
12 of these projects have no number: additionality, quantification or both have no public grade of their type of project that applies to them yet. Their pages give the reason and how many negative facts were found; the analysis is in Premium.
- Analysis: No rating yet
- Analysis: No public grade applies yet
- Analysis: No rating yet
- Analysis: Re-assessment pending
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: Not yet assessable
- Analysis: No rating yet
- Analysis: Re-assessment pending
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No public grade applies yet
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: Re-assessment pending
- Analysis: Not registered
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No public grade applies yet
- Analysis: Re-assessment pending
- Analysis: No rating yet
- Analysis: No public grade applies yet
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: Not yet assessable
- Analysis: Not registered
- Analysis: Not registered
- Analysis: Not registered
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: Re-assessment pending
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No public grade applies yet
- Analysis: No public grade applies yet
- Analysis: No rating yet
- Analysis: No public grade applies yet
- Analysis: No public grade applies yet
- Analysis: No public grade applies yet
- Analysis: No rating yet
- Analysis: Re-assessment pending
- Analysis: Re-assessment pending
- Analysis: Not registered
- Analysis: No public grade applies yet
- Analysis: No public grade applies yet
- National Programme for Energy Efficiency Improvement in the Brick Manufacturing Sector in BangladeshAnalysis: No public grade applies yet
- National Programme for Energy Efficiency Improvement in the Brick Manufacturing Sector in BangladeshAnalysis: Not registered
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: Not registered
- Analysis: No rating yet
- Analysis: No rating yet
- Analysis: Not registered