3 MW Biomass-fired cogeneration project at Tamil Nadu
#183of 196 in Biomass#6of 7 in Tamil Nadu#391of 421 in Universal Carbon Registry (UCR)
Audit Analysis
This 3 MW biomass cogeneration project in Tamil Nadu is registered under the UCR registry using the AMS-I.C. methodology, but the available evidence is extremely limited to a single PDD dated after the crediting period ended. No additionality assessment, verification report, monitoring data, or VVB identification could be found, leaving the core integrity claims largely unverified. The 0% leakage deduction rests on a bare 'deemed negligible' justification without quantitative support.
Red Flags
- No additionality test or VVB verification of additionality found in any available document
- PDD is dated 19 October 2023, after the crediting period ended on 31 December 2022, raising questions about the document's provenance and whether it reflects the original project design
- No verification report, monitoring report, or VVB report is available — the entire 75,744 tCO₂e claim is unverified
- No VVB (verification body) is identified in the extracted record
- 0% leakage deduction justified only as 'deemed negligible' with no quantitative analysis for a biomass supply-chain project
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
No additionality test documented
No buffer pool; no reversal data
0% deduction, minimal justification
Project-specific, no reassessment date
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →