30 MW WHR Project of Hongshi Group
#141of 204 in China#127of 213 in CDM (UNFCCC)#13of 17 in ACM0004
Audit Analysis
A 30 MW waste-heat-recovery CDM project in China with VVB-confirmed additionality (barrier test) and a reputable verifier (TÜV NORD CERT), but undermined by a 0% leakage deduction with no supporting justification in the monitoring report, a contradiction between the PDD's jurisdictional baseline and the monitoring report's project-specific baseline, and multiple material findings and corrective actions that signal data-quality weaknesses. ERR delivery is roughly 90% of the pro-rata expectation, which is reasonable, but the baseline and leakage gaps create meaningful over-crediting risk.
Red Flags
- Leakage deduction of 0% with justification recorded as 'not addressed' in the 2013 monitoring report, while the 2007 validation report had initially deemed it negligible — the later, more specific document provides no quantitative or qualitative basis for the zero deduction.
- Baseline method contradiction: the PDD (2010) describes a jurisdictional baseline, but the monitoring report (2013) refers to a project-specific baseline; the more recent document weakens the baseline's robustness and raises over-crediting risk.
- Five corrective actions and three compliance-level findings were raised during verification, including inconsistencies in boiler parameters between the registered PDD and on-site data, and missing procedures for monitoring data adjustments and internal audits.
- No free, prior, and informed consent (FPIC) or grievance mechanism is documented in any available record, despite safeguards being mentioned in the project description.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 83,532 | 0 | 83,532 | |
| 2011 | 170,965 | 0 | 170,965 | |
| 2014 | 502,922 | 0 | 502,922 | |
| Total | 757,419 | 0 | 757,419 |
Risk Indicators
VVB-confirmed barrier test
WHR project – low reversal risk
0% deduction, justification not addressed
Method contradiction: jurisdictional vs project-specific
Mentioned but FPIC and grievance mechanism not documented
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →