Skip to main content
GSOtherIndiaACM0002

40 MW Orange Charanka Solar Power Project in Gujarat, India

GS-1377 ↗ · current registry ID: GS5866

#243of 1935 in Renewable energy#121of 975 in India#90of 1801 in Gold Standard (GS)#176of 1287 in ACM0002

6.2/ 10
Integrity
6.8
Transparency
5.8
Claim Safety
6.2
Documentation
5.5

Audit Analysis

A 40 MW solar PV avoidance project under Gold Standard with VVB-confirmed additionality and a recent grid emission factor, but hampered by a missing leakage justification, an unverified ERR figure, and seven cross-document contradictions that reduce confidence in the data record. The project is CORSIA-eligible and uses a standard methodology (ACM0002 v17.01), but the absence of a verified emissions reduction figure and the unresolved discrepancy between claimed ERR values (380,092 vs 167,298) create meaningful over-crediting uncertainty.

Red Flags

  • Leakage deduction of 0% with justification recorded as 'not addressed' in the verification report (2024-05-29), while the monitoring report (2024-05-07) claims it was 'deemed negligible' — the higher-priority verification report does not support the 0% deduction
  • No verified ERR figure is available (total_err_verified is absent from the record), and the two claimed ERR values (380,092 from the appendix dated 2024-12-07 and 167,298 from the monitoring report dated 2024-05-07) differ by a factor of 2.3, making it impossible to confirm the actual emissions reduction delivered
  • Three Corrective Action Requests were raised in the verification report, indicating unresolved compliance issues at the time of verification
  • Seven contradictions across documents (leakage, baseline method, ERR, additionality test, FPIC, reversal events, crediting period) signal inconsistent record-keeping

Credit Vintages

IssuedRetiredAvailable
2017
24,67324,6730
2018
85,10585,1050
2019
84,13784,1370
2020
86,08686,06521
2021
82,587082,587
2022
84,711084,711
Total447,299279,980167,319

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal risk

Leakage

0% deduction, justification not addressed in verification report

Baseline

Project-specific baseline, reassessed 2024

Safeguards

FPIC conducted, grievance mechanism present

Double-claim

CORSIA-eligible, CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents