8.75MW Bundle Wind Power Project in Maharashtra
#121of 770 in Renewable energy#68of 387 in India#19of 213 in CDM (UNFCCC)#37of 417 in AMS-I.D
Audit Analysis
A CDM wind power project in Maharashtra with a VVB-confirmed investment additionality test and a reasonable 0% leakage deduction, but undermined by multiple material findings on monitoring plan accuracy, a contradiction in baseline method between the validation and monitoring reports, and the absence of verified ERR figures. The project's safeguards documentation is thin, with no FPIC or grievance mechanism on record.
Red Flags
- Material findings reveal the registered monitoring plan did not match actual site conditions: meters are located at the MSEDCL sub-station rather than the project site, and the data source was a Credit Report rather than direct MSEDCL readings
- Contradiction in baseline method: the 2007 validation report describes a jurisdictional baseline while the 2021 monitoring report describes a project-specific baseline
- Two different total ERR figures (70,262 and 11,570) appear in the same 2021 monitoring report without clear reconciliation
- No FPIC or grievance mechanism documentation found in any available record
- Grid emission factor of 0.92 is ex-ante (2007) and was flagged in material findings as not ex-post
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 32,977 | 0 | 32,977 | |
| 2014 | 23,385 | 0 | 23,385 | |
| 2022 | 51,497 | 0 | 51,497 | |
| Total | 107,859 | 0 | 107,859 |
Risk Indicators
VVB-confirmed investment test
No buffer pool or explicit permanence mechanism documented
0% with quantified justification, appropriate for wind
Method contradicted across documents; ex-ante grid EF from 2
Safeguards mentioned and benefit sharing described, but no F
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →