Cabo Negro Wind Farm Project, Phase 1
#996of 1861 in Renewable energy#18of 36 in Chile#740of 1514 in CDM (UNFCCC)#3of 6 in AMS-I.A
Audit Analysis
The Cabo Negro Wind Farm Phase 1 is a CDM-registered wind project in Chile with confirmed additionality via a combined test verified by TÜV NORD CERT. However, the validation report identified five material findings including calculation errors and a crediting-period inconsistency, and no corrective actions are recorded. The absence of any monitoring-period data and a project-specific (rather than grid-average) baseline limit confidence in the claimed 104,360 tCO₂e lifetime reduction.
Red Flags
- Five material findings in the validation report include an incorrect calculation of average fuel savings per MWh and an inconsistency in crediting-period duration (7 vs 10 years), yet no corrective actions are recorded in the extracted record
- No monitoring-period data or verified ERR is available in the extracted documents, making it impossible to confirm actual delivery against the 104,360 tCO₂e lifetime claim
- Baseline is project-specific rather than a jurisdictional grid-average, which is less conservative for a wind project displacing grid electricity
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-confirmed
Avoidance project, no reversal risk
0% deemed negligible, reasonable for wind
Project-specific, not grid-average
Mentioned but details not extracted
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →