GIRESUN LANDFILL GAS (LFG) PROJECT
#19of 64 in Methane#65of 121 in Turkey#284of 629 in Verra (VCS)#16of 53 in ACM0001
Audit Analysis
The Giresun LFG project is a standard landfill gas-to-energy project under VCS methodology ACM0001 v19.0 with VVB-confirmed additionality and a 7-year crediting period. However, the available record contains only a validation report and PDD with no monitoring data, low extraction confidence, and two inter-document contradictions (FPIC status and leakage justification) that reduce confidence in the overall evidence base.
Red Flags
- No monitoring reports or verified emissions data found in the extracted record — the project has been in its crediting period since April 2021 but no MRV evidence is available
- FPIC contradiction: the validation report (June 2025) states FPIC was not conducted, while the PDD (January 2023) indicates it was; the more recent and authoritative validation report is privileged
- Low extraction confidence across the document set, meaning key details may have been missed or misread
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test; capture not legally required
N/A — LFG combustion, no storage or reversal risk
0% deduction with quantified justification (validation repor
Project-specific modeled baseline; no reassessment on record
Grievance mechanism present; FPIC status contradictory betwe
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →