Guangzhou Huadu Shiling LFG Power Generation Project
#11of 204 in China#34of 629 in Verra (VCS)#3of 53 in ACM0001
Audit Analysis
A landfill gas-to-power project in China with a VVB-verified combined additionality test, no reversal events, and a reasonable leakage justification. The project-specific baseline and a material finding about generator reduction (4 to 3) introduce moderate risk, while several data extraction inconsistencies within the same verification report create uncertainty around safeguards and FPIC documentation.
Red Flags
- Material finding: gas generators reduced from four to three due to equipment failure and decreasing LFG production, indicating operational fragility that could affect future credit generation
- Contradiction on whether LFG capture is legally required (PDD says yes, 2024 monitoring report says no) — if legally required, additionality is weakened
- Multiple fields (FPIC, grievance mechanism, benefit sharing, safeguards) show contradictory true/false values within the same verification report dated 2024-10-09, suggesting extraction or reporting inconsistencies
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2020 | 145,096 | 145,096 | 0 | |
| 2021 | 92,702 | 92,702 | 0 | |
| 2022 | 25,228 | 0 | 25,228 | |
| Total | 263,026 | 237,798 | 25,228 |
Risk Indicators
Combined test, VVB-verified
No reversal events, continuous process
0% deemed negligible, reasonable for LFG
Project-specific, measured
Documented but extraction contradictions
CORSIA excluded, CCP not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →