Guantao Qingfeng Biological Manure Management Greenhouse Gas Emission Reduction Project
#121of 209 in China#393of 632 in Verra (VCS)#8of 13 in AMS-III.F
Audit Analysis
A VCS-registered anaerobic manure digestion project (AMS-III.F) in China with a verified first monitoring period, but the verification report identified four material findings including calculation errors in methane conversion factors, a weak additionality sensitivity profile, and an unexplained 42% free-fertilizer distribution. The project's integrity is materially undermined by these unresolved issues, and the leakage treatment lacks a coherent justification across documents.
Red Flags
- Sensitivity analysis in the verification report showed the IRR benchmark is met with less than 10% change in revenue or costs, indicating marginal additionality that the VVB flagged as requiring further justification
- 42% of the biogas-derived fertilizer is distributed free of charge, yet no evidence or rationale was provided to demonstrate this does not undermine the investment additionality test
- MCFj and Bo values used in the original emission-reduction calculations were incorrect; the verification report required correction to MCFj = 73% and Bo = 0.13, meaning previously reported ER figures may be unreliable
- Leakage deduction is 0% with the verification report stating the issue was 'not addressed' while the monitoring report claims it was 'deemed negligible' — no quantitative or qualitative justification is documented in either source
- The JVVR incorrectly referenced methodology AMS-III.D instead of the applicable AMS-III.F, raising questions about the rigor of the verification process
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2022 | 56,349 | 3,221 | 53,128 | |
| 2023 | 10,258 | 9,815 | 443 | |
| Total | 66,607 | 13,036 | 53,571 |
Risk Indicators
VVB-confirmed but sensitivity analysis marginal; 42% free di
No reversal events, but buffer pool percentage not stated
0% deduction with no documented justification in verificatio
Project-specific modeled baseline; reassessment not yet due
FPIC conducted, grievance mechanism in place, benefit sharin
CORSIA eligibility and CCP status not stated in available do
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →