UCRGummidipoondi Tamil Nadu IndiaACM0012

KIL Waste Heat to Power project, India

UCR-380 ↗

#188of 202 in Industrial#226of 421 in Universal Carbon Registry (UCR)#13of 15 in ACM0012

3.3/ 10
Integrity
4.0
Transparency
2.0
Claim Safety
4.0
Documentation
2.5

Audit Analysis

The KIL Waste Heat to Power project (UCR-380) is a straightforward industrial waste-heat-to-power installation under the well-established ACM0012 v6.0 methodology, but the available evidence is limited to a single PDD with no verification report, monitoring report, or VVB documentation. Key integrity elements such as additionality testing, verified emissions reductions, and buffer-pool arrangements are absent from the extracted record, making it impossible to independently confirm the claimed 44,582 tCO₂e over the 2018–2022 crediting period.

Red Flags

  • No additionality test type or VVB confirmation found in the available PDD, leaving the core additionality claim unverified
  • Total verified ERR is absent; the 44,582 tCO₂e figure is uncorroborated by any monitoring or verification report
  • No VVB (verification body) is identified in the record, raising questions about independent third-party assurance
  • Only one document (the PDD) is available; no verification report, monitoring report, or VVB statement was found

Credit Vintages

Issuance data not yet available — check back soon.

Risk Indicators

Additionality

No additionality test or VVB confirmation found

Permanence

No buffer pool; low inherent risk but unaddressed

Leakage

0% deemed negligible; no quantified justification

Baseline

Project-specific; no reassessment date recorded

Safeguards

Mentioned with benefit sharing; FPIC and grievance mechanism

Double-claim

CORSIA and CCP status not stated in available records

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-20ACM0012

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents