KIL Waste Heat to Power project, India
#188of 202 in Industrial#226of 421 in Universal Carbon Registry (UCR)#13of 15 in ACM0012
Audit Analysis
The KIL Waste Heat to Power project (UCR-380) is a straightforward industrial waste-heat-to-power installation under the well-established ACM0012 v6.0 methodology, but the available evidence is limited to a single PDD with no verification report, monitoring report, or VVB documentation. Key integrity elements such as additionality testing, verified emissions reductions, and buffer-pool arrangements are absent from the extracted record, making it impossible to independently confirm the claimed 44,582 tCO₂e over the 2018–2022 crediting period.
Red Flags
- No additionality test type or VVB confirmation found in the available PDD, leaving the core additionality claim unverified
- Total verified ERR is absent; the 44,582 tCO₂e figure is uncorroborated by any monitoring or verification report
- No VVB (verification body) is identified in the record, raising questions about independent third-party assurance
- Only one document (the PDD) is available; no verification report, monitoring report, or VVB statement was found
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
No additionality test or VVB confirmation found
No buffer pool; low inherent risk but unaddressed
0% deemed negligible; no quantified justification
Project-specific; no reassessment date recorded
Mentioned with benefit sharing; FPIC and grievance mechanism
CORSIA and CCP status not stated in available records
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →