Vai al contenuto principale
GS Biogas - Electricity Thailand Documentazione completa General Methodology v2.0

UPOIC Wastewater Treatment for Energy Generation, Krabi

GS-1135 ↗

5.2 / 10
Integrity
5.8
Transparency
4.6
Claim Safety
5.0
Documentation
5.1

Score Breakdown

Integrity

verified Additionality was confirmed by the VVB using an investment test, which is stronger than an unverified claim.

missing Leakage justification is marked as not addressed, and reversal risk is only described in general terms rather than with a buffer or event record.

Transparency

verified The monitoring period and crediting period are both stated, and the VVB is named as Swiss Carbon Assets Ltd.

missing No verified emission reduction totals, usage monitoring method, or FNRB information were found in the extracted record.

Claim Safety

verified The project uses a project baseline and a 0% leakage deduction is stated, which helps limit over-crediting risk if the underlying justification is sound.

missing CORSIA eligibility is not stated and CCP status is only noted as not mentioned, leaving dual-claim risk unresolved.

Documentation

verified Eleven documents were used and the extraction confidence is medium rather than low.

missing Material findings required corrective action on monitoring calculations and sustainable development reporting, showing the documentation needed cleanup.

Detailed Analysis

Integrity

The verification record confirms additionality through an investment test and says the VVB accepted the project, which supports the core project logic. However, leakage justification is marked as not addressed, buffer pool coverage is not found, and reversal handling is only described in broad terms. The project therefore looks moderately credible, but not strongly insulated against baseline or permanence concerns.

Transparency

The documents identify the VVB, the monitoring period, and the crediting period, which helps anchor the record. Still, the extracted facts do not include verified emission reduction totals, a usage monitoring method, or any FNRB method/value, so the MRV trail is incomplete. The medium extraction confidence also suggests at least one source was not perfectly readable, which lowers transparency confidence.

Claim Safety

Claim safety is helped by the project-specific baseline and the stated 0% leakage deduction, but the leakage rationale itself is not clearly documented. CORSIA eligibility is not stated and CCP status is only noted as not mentioned, so there is no strong evidence that dual-market claim risk is excluded. The contradiction on leakage treatment, where one document reportedly quantified it and a later one says it was not addressed, further weakens confidence.

Documentation

The record draws on eleven documents, and the extraction confidence is medium, which is acceptable but not strong. Two corrective-action items were raised in verification, including a wrong MCFww value and missing sustainable development monitoring results, indicating that the documentation package needed revision. The crediting period also appears in two different forms across documents, which suggests version control issues even though the later date was likely the more authoritative record.

Overall

I privileged the later-dated values where contradictions existed, especially the 2016/2018 records over earlier 2015 entries, because they appear to reflect updated verification or revised reporting. That said, the contradictions on additionality test type, benefit sharing, leakage treatment, and crediting period all point to versioning and consistency issues, so I reduced confidence accordingly. The project is not a clear red-flag case, but the evidence base is only moderately reliable and leaves several important claim-safety questions unresolved.

Audit Analysis

This project has some positive integrity signals, including VVB-confirmed additionality and a stated leakage deduction of 0%, but key risk areas are weakly documented. Transparency is limited by missing verification totals, no usage monitoring method, and no clear public evidence on CORSIA or CCP status. Overall, the record is usable but not especially robust, with several unresolved documentation gaps and a few contradictions that reduce confidence.

Project Description

Developer: Swiss Carbon Assets Ltd. Type: Biogas - Electricity Size: Small Scale Methodology: AMS-I.D. Grid connected renewable electricity generation Crediting period: 2011-10-18 → 2021-10-17 Estimated annual credits: 18001 tCO2e SDGs: Goal 13: Climate Action

Red Flags

  • Leakage is not clearly justified in the extracted record, even though the project type can have leakage considerations.
  • No buffer pool percentage, reversal history, or verified usage monitoring method was found in the available documents.

Credit Vintages

Issued Retired Available
2014
9,746 0 9,746
Total 9,746 0 9,746

Cosa migliorerebbe questo punteggio

  • Publish a clear leakage assessment, including the basis for the 0% deduction and any supporting calculations.
  • Provide verified emission reduction totals, usage monitoring details, and explicit CORSIA/CCP status in the registry record.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

No buffer pool found

Leakage

0% deduction with weak justification

Baseline

Project baseline, reassessment not stated

Safeguards

FPIC and grievance mechanism present

Double-claim

CORSIA/CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-19 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti