14.2 MW Wind Project in Karnataka
#483of 770 in Renewable energy#3of 17 in Karnataka India#41of 421 in Universal Carbon Registry (UCR)
Audit Analysis
A 14.2 MW grid-connected wind project in Karnataka using the standardized AMS-1.D methodology with a jurisdictional baseline and a conservative lifetime claim of 25,746 tCO2. The project shows no material findings or corrective actions, but the available record consists solely of the PDD — no verification report, monitoring report, or VVB documentation was found, leaving additionality, permanence, and actual delivery unverified.
Red Flags
- No verification body (VVB) identified in the available record; additionality and baseline compliance cannot be independently confirmed
- Only a single document (the PDD dated 2022-08-02) is available; no monitoring report or verification report exists in the extracted record, so the 25,746 tCO2 claim is unverified
- No buffer pool or explicit permanence mechanism is stated, leaving reversal risk for the wind assets unaddressed in the available documentation
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
Test presumed in PDD but unverified; no VVB identified
No buffer pool or permanence mechanism stated; no reversal e
0% deduction, deemed negligible — appropriate for grid-conne
Jurisdictional method used; no reassessment date found in re
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →