8.4 MW Bundled Wind Power Project by Meghmani Organics Limited
#518of 770 in Renewable energy#12of 42 in Gujarat India#86of 421 in Universal Carbon Registry (UCR)#221of 417 in AMS-I.D
Audit Analysis
An 8.4 MW wind project in Gujarat, India, registered under the UCR standard using the AMS-I.D. methodology, with a jurisdictional baseline and a deemed-negligible leakage treatment. The project's integrity is supported by a standardized methodology and no material findings, but the complete absence of any verification or monitoring report, an unidentified VVB, and no verified emissions-reduction figure leave critical claims unconfirmed. The documentation record consists solely of a single PDD, making independent assessment of additionality, permanence, and actual delivery impossible.
Red Flags
- No verification report or monitoring report was available in the extracted record; only the PDD (dated 2025-03-28) was used, leaving the claimed 13,245 tCO2e entirely unverified
- No VVB is identified in the available documents, so additionality verification and independent review cannot be confirmed
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel or double-claiming risk unassessed
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
Methodology requires it but no specific test or VVB confirma
Low inherent risk (wind) but no buffer pool documented
Deemed negligible, consistent with grid-displacement project
Jurisdictional method is sound; reassessment not yet due (~2
Mentioned in PDD but FPIC and grievance mechanism not confir
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →