3 MW Rice Husk based Cogeneration Project at Ganeshpur, Basti (U.P.)
#184of 196 in Biomass#392of 421 in Universal Carbon Registry (UCR)#38of 42 in AMS-I.C
Audit Analysis
This 3 MW rice husk cogeneration project under the UCR registry has only a Project Design Document in the available record, with no verification report, monitoring report, or VVB assessment. Key integrity elements — additionality testing, grid emission factor, buffer pool, and baseline reassessment — are absent from the extracted data, making it impossible to independently validate the 58,902 claimed emission reduction units. The project's fundamental design (waste biomass to electricity) is reasonable, but the evidentiary base is too thin to support a confident quality assessment.
Red Flags
- No verification report, monitoring report, or VVB report found in the available record — only a PDD is present
- No grid emission factor or grid EF year stated, making the baseline calculation unverifiable
- No additionality test type or VVB confirmation of additionality found in the extracted data
- No buffer pool percentage stated, leaving permanence risk unaddressed in the available documentation
- No verified ERR figure available to validate the 58,902 claimed units over the crediting period
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
No additionality test or VVB confirmation found
No buffer pool stated; no reversal data
0% deemed negligible; plausible but unquantified
Project-specific; no grid EF or reassessment date
Safeguards and benefit sharing mentioned; no FPIC or grievan
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →