Aperam BioEnergia
Score Breakdown
Integrity
verified The verification report (2025) reports no material findings.
missing Leakage is described as quantified, but the actual leakage deduction percentage was not found in the extracted record, weakening the integrity of net removals.
Transparency
verified The VVB is identified as EnergyLink Services in the verification report (2025).
missing Claimed vs verified removal totals were not found in the extracted record, reducing auditability of outcomes.
Claim Safety
inferred Additionality is described as an investment test, but confirmation by the VVB was not found in the extracted record.
missing CORSIA eligibility and CCP status were not found in the extracted record, increasing uncertainty for downstream claims and labeling.
Documentation
verified Ten documents were used with medium extraction confidence, suggesting a moderate evidence base.
missing The evidence document list is not specific (listed as "unknown"), and multiple corrective actions in the verification report (2025) indicate documentation/MRV gaps.
Detailed Analysis
Integrity
The project applies the Puro.earth Biochar Methodology (Edition 2022 v3) and uses a project-specific baseline approach, but the timing of any baseline reassessment was not found in the extracted record. The verification report (2025) reports no material findings, which is positive, yet it also requires corrective actions on biochar stock reporting and multiple LCA elements, which can directly affect quantified removals. Leakage is described as quantified, but the leakage deduction percentage was not found in the extracted record, leaving net climate benefit uncertain. Buffer pool contribution and any reversal events were not found in the extracted record, limiting assessment of permanence controls for stored carbon in biochar.
Transparency
The verification report (2025) identifies the VVB as EnergyLink Services and provides a defined monitoring period (2024-03-01 to 2025-03-31). However, the extracted record does not include total removals claimed or verified, preventing a basic reconciliation of issuance quantities to monitored outcomes. Key MRV descriptors such as the usage monitoring method and any assumed/verified usage rate were not found in the extracted record, reducing replicability of the accounting. Registry details are minimal (listed as "other"), and the evidence document reference is not specific ("unknown").
Claim Safety
Additionality is described as an investment test, but confirmation by the VVB was not found in the extracted record, which weakens confidence for high-integrity claims. The baseline is project-specific and key quantification items (verified removals, leakage deduction value) were not found in the extracted record, elevating over-crediting risk. CCP status and CORSIA eligibility were not found in the extracted record, creating uncertainty for buyers about how the credits can be marketed and whether any additional eligibility screens apply. The presence of corrective actions in the verification report (2025) related to LCA and stock reporting further increases the risk that early claims could be revised.
Documentation
The extracted record indicates 10 documents were used and the minimum extraction confidence is medium, supporting a mid-range documentation score. Still, the evidence document list is not specific (shown as "unknown"), which makes it hard to trace key assertions back to named sources. The verification report (2025) includes multiple corrective actions (biochar stock reporting and several LCA calculation inputs), suggesting that documentation and data systems were not fully satisfactory at the time of verification. Crediting period information was not found in the extracted record, limiting assessment of recency and program-cycle completeness.
Overall
No contradictions were flagged in the extracted record, so no cross-document discrepancies could be resolved or prioritized. The overall score is driven down primarily by missing quantified outcomes (claimed/verified removals), missing leakage deduction value despite leakage being described as quantified, and the presence of multiple corrective actions in the verification report (2025) affecting core accounting elements. Safeguards signals (FPIC and a grievance mechanism) and the absence of material findings in the verification report (2025) provide some support, but do not offset the MRV and disclosure gaps. Note: gate rules may cap transparency if documentation were scored below 3.0, and cap overall if integrity were below 4.0 (not triggered by these scores).
Audit Analysis
The project is assessed under the Puro.earth Biochar Methodology and includes some key safeguards signals (FPIC and a grievance mechanism). However, core quantification and MRV elements (verified removals, leakage deduction value, and several monitoring parameters) were not found in the extracted record, and the verification report lists multiple corrective actions, increasing uncertainty and over-crediting risk.
Project Description
Aperam BioEnergia operates in Brazil’s forestry and renewable energy sectors, producing 450,000 tons of charcoal annually with FSC-certified eucalyptus forests. Its biochar project improves soil, sequesters carbon, and aids local farming. Certified under ISO standards and issuing carbon credits via Puro.Earth, Aperam drives sustainability, carbon removal, and wildlife conservation.
Red Flags
- Verified and claimed removal totals were not found in the extracted record, limiting confidence in credit quantity.
- The verification report (2025) lists multiple corrective actions related to biochar stock reporting and LCA calculations, indicating unresolved MRV weaknesses at verification time.
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2022 | 4,735 | 4,735 | 0 | |
| 2023 | 18,698 | 18,698 | 0 | |
| 2024 | 75,450 | 75,450 | 0 | |
| 2025 | 16,191 | 16,191 | 0 | |
| 2026 | 46,433 | 46,433 | 0 | |
| Total | 161,507 | 161,507 | 0 |
Cosa migliorerebbe questo punteggio
- Disclose and reconcile total removals claimed vs verified for the monitoring period, including calculation spreadsheets and issuance/retirement links on the registry.
- Publish the quantified leakage deduction (percentage and rationale) and close the verification corrective actions on biochar stock reporting and LCA inputs with documented evidence.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
Investment test stated; VVB confirmation not found
Buffer pool and reversal controls not evidenced in extracted record
Leakage described as quantified; deduction value not found
Project-specific baseline; reassessment timing not found
FPIC and grievance mechanism documented
CORSIA and CCP status not found in extracted record
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Registry Documents
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →