Skip to main content
VCSEnergy industries (renewable/non-renewable sources); Waste handling and disposalTurkey Registry: RegisteredAMS-III.D

CEKEREK BIOGAS POWER PLANT

VCS-4403 ↗

#18of 111 in Biogas#56of 121 in Turkey#247of 629 in Verra (VCS)#9of 62 in AMS-III.D

5.6/ 10
Integrity
6.5
Transparency
4.5
Claim Safety
6.0
Documentation
4.5

Audit Analysis

The Cekerrek Biogas Power Plant is a VCS-registered biogas energy project in Turkey using the well-established AMS-III.D methodology, with VVB-confirmed additionality via a barrier test and no reversal risk inherent to the energy sector. However, the project relies on a project-specific baseline, lacks a monitoring report in the available record, and the low extraction confidence across ten documents limits assurance on data completeness. Three contradictions between the PDD and validation report were identified and resolved in favour of the more recent VVB assessment.

Red Flags

  • Low extraction confidence across the document set means at least one key document was poorly readable, reducing assurance on the accuracy of extracted figures.
  • No monitoring report or monitoring period was found in the available record; the only ERR figures (167,363 tCO₂e claimed and verified) appear to be the lifetime ex-ante estimate, so actual delivery performance cannot be assessed.
  • 17 Corrective Action Requests were raised during validation (all closed), indicating a non-trivial number of issues the VVB needed to resolve before sign-off.
  • A Forward Action Request regarding future changes in the manure supplier farm list remains open, introducing a minor forward-looking risk to feedstock continuity.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

Barrier test, VVB-confirmed

Permanence

Energy project, no reversal risk

Leakage

0% deduction, deemed negligible (biogas)

Baseline

Project-specific, measured, no reassessment data

Safeguards

FPIC, grievance mechanism, safeguards documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-24AMS-III.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.