CGN Minqin Hongshagang Xianshuijing Wind Power Project
#1413of 1935 in Renewable energy#866of 1084 in China#1146of 1459 in CDM (UNFCCC)#1085of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China with a jurisdictional baseline and a well-understood technology (ACM0002), but the available record is limited to validation-stage documents. A material finding (CAR-1) flagged an emission-factor calculation inconsistency in the PDD that required corrective action, and no post-implementation monitoring or verification reports were found in the extracted record.
Red Flags
- Material finding CAR-1: the PDD's operational-monitoring emission-factor calculation was inconsistent with the CDM Tool v7.0, requiring a corrective action to revise the PDD before credit issuance.
- No verification or monitoring reports were found in the extracted record; the only ERR figure (491,932 tCO₂e) is the ex-ante PDD estimate confirmed at validation, not a post-implementation measurement.
- Additionality test type and VVB confirmation of additionality are not stated in the available documents, leaving the additionality basis unverified in the extracted record.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2019 | 327,251 | 0 | 327,251 | |
| Total | 327,251 | 0 | 327,251 |
Risk Indicators
Test type and VVB confirmation not stated in extracted recor
Wind avoidance project – no carbon storage, low reversal ris
0 % deduction, deemed negligible – consistent for onshore wi
Jurisdictional grid EF (2017), reassessed at project start (
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →