Domestic Biogas Project for rural households in India

GS-1614 ↗ · current registry ID: GS6275

#65of 111 in Biogas#301of 387 in India#328of 426 in Gold Standard (GS)#19of 26 in AMS-I.E

4.7/ 10
Integrity
4.0
Transparency
5.5
Claim Safety
4.5
Documentation
5.5

Audit Analysis

A long-running domestic biogas project (since 2017) on Gold Standard using the well-established AMS-I.E. methodology, but the 2024 verification report raised 12 material findings and 7 corrective actions, including a finding of adverse relevance that pre-project biogas units may have been included in credit calculations. The project's avoidance-based design limits permanence risk, but the volume of MRV and transparency deficiencies, combined with unresolved contradictions in key parameters (leakage, FNRB, FPIC), significantly undermines confidence in the integrity and accuracy of the claimed reductions.

Red Flags

  • Finding of Adverse Relevance (FAR): the project proponent was instructed not to include biogas units commissioned before the project start date, indicating potential over-crediting from pre-existing infrastructure
  • 12 material findings and 7 corrective actions raised in the 2024 verification report, covering sampling transparency, ER calculation errors, missing SDG outcomes, and unaddressed removal of digesters in Uttarakhand
  • Leakage deduction contradicts sharply between verification reports: 5% (2024) vs 95% (2022), a 19-fold difference that raises serious data-reliability questions
  • FPIC status is contradictory: the 2022 validation report records FPIC as conducted, but the 2024 monitoring report records it as not conducted
  • No buffer pool percentage is stated in any available document, leaving permanence risk unquantified

Credit Vintages

IssuedRetiredAvailable
2017
29,31329,3130
2018
41,73241,7320
2019
45,02945,0290
2020
42,71042,7100
2021
41,76141,203558
2022
17,77811,4426,336
2023
3,4871,8801,607
Total221,810213,3098,501

Risk Indicators

Additionality

Combined test present but FAR on pre-project units; VVB conf

Permanence

Avoidance project; no reversal events in most recent monitor

Leakage

5% quantified (2024) but contradicted by 95% in 2022 report

Baseline

Project-specific baseline; last reassessed 2022

Safeguards

Grievance mechanism present; FPIC status contradictory acros

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25AMS-I.E.

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents