GS1247 VPA 62 Improved Kitchen Regimes: Kayonza District Borehole Project, Rwanda
Score Breakdown
Integrity
verified The monitoring report states leakage was deemed negligible, which is better than an unaddressed leakage issue.
missing A reversal event was reported in the monitoring report, and no buffer pool percentage is stated in the extracted record.
Transparency
verified The monitoring period is clearly stated in the monitoring report, and the usage monitoring method is described as an annual survey.
missing The VVB name, quantified ERR totals, and registry completeness details are not found in the extracted record.
Claim Safety
verified The monitoring report gives a verified usage rate of 90%, which is preferable to relying only on the assumed 95%.
missing The baseline method is not stated, and the contradiction on leakage treatment shows the PDD did not address leakage while the later monitoring report says it is negligible.
Documentation
verified Two document types were used, and the extraction confidence is high.
missing The crediting period is not stated, and several core fields are missing or not quantified, including additionality test details and corrective actions.
Detailed Analysis
Integrity
The monitoring report provides some support for project integrity by stating that leakage was deemed negligible and by reporting a verified usage rate of 90%. However, integrity is weakened by the reported reversal event, where KAY016 MUGANZA was non-functional for 30 days, and by the absence of a stated buffer pool percentage or baseline method in the extracted record. Additionality is not well evidenced because the additionality test type and VVB confirmation are not found in the available documents.
Transparency
Transparency is moderate at best because the monitoring period, annual survey usage monitoring method, and Gold Standard registry context are available. At the same time, the VVB name is not found, total ERR claimed and verified are not provided, and the registry completeness around issuance and verification is therefore limited. The high extraction confidence helps, but the documentation remains incomplete for public claim checking.
Claim Safety
Claim safety is constrained by missing baseline detail and by the fact that the project relies on a project-specific monitoring narrative rather than a clearly stated, recently reassessed baseline. The verified usage rate of 90% is lower than the assumed 95%, which suggests some over-crediting risk, although the difference is not extreme. The contradiction on leakage is important: the PDD did not address leakage, while the later monitoring report says it is negligible, so I privileged the more recent monitoring report because it is closer to the monitored period and more specific.
Documentation
Documentation quality is only moderate because the record includes a monitoring report and PDD, but several core fields are missing or unstated, including the baseline method, additionality test type, VVB name, buffer pool percentage, and crediting period. The extraction confidence is high, which avoids a penalty, but the absence of quantified ERR totals and corrective actions still limits auditability. The project also has a reported reversal event, which should have been accompanied by clearer follow-up documentation.
Overall
Overall, I privileged the monitoring report over the older PDD where the two conflict, because it is more recent and directly reflects the monitored period. Specifically, I used the 90% verified usage rate instead of the earlier 100% figure, and I accepted the monitoring report’s negligible leakage statement over the PDD’s lack of leakage treatment. The reported reversal event and the missing baseline, VVB, and buffer pool details reduce confidence in the crediting claim and keep the project in a mid-low quality range.
Audit Analysis
This project has some positive safeguards and a documented monitoring period, but the evidence base is thin and there are reliability concerns. The monitoring report shows a 90% verified usage rate, a negligible leakage claim, and one reported reversal/non-functionality event, which weakens permanence and claim confidence.
Project Description
Developer: CO2balance UK ltd Type: Energy Efficiency - Domestic Size: Micro Scale Methodology: GS TPDDTEC v 1. Crediting period: 2016-08-25 → 2023-08-25 Estimated annual credits: 10000 tCO2e SDGs: Goal 5: Gender Equality, Goal 3: Good Health and Well-Being, Goal 6: Clean Water and Sanitation, Goal 13: Climate Action
Red Flags
- A reversal event was reported for one borehole being non-functional for 30 days, which raises permanence and delivery-risk concerns.
- Key documentation elements are missing or unstated, including the baseline method, VVB name, buffer pool percentage, and any quantified ERR totals.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 3,726 | 3,726 | 0 | |
| 2017 | 10,000 | 10,000 | 0 | |
| 2018 | 10,000 | 10,000 | 0 | |
| 2019 | 8,331 | 7,847 | 484 | |
| 2020 | 2,568 | 2,568 | 0 | |
| Total | 34,625 | 34,141 | 484 |
Cosa migliorerebbe questo punteggio
- Provide a complete verification package with the VVB name, quantified ERR totals, baseline method, and any corrective actions taken after monitoring.
- Document reversal handling, buffer pool coverage, and a clear leakage assessment with quantified treatment and justification.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
Additionality not evidenced in extracted record
Reversal event reported
Negligible claim but no quantified deduction
Baseline method not stated
FPIC and grievance mechanism documented
CORSIA/CCP status not stated
Where to buy
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →