Migros PV Bundle
#767of 770 in Renewable energy#14of 14 in TR#24of 32 in Intl. Carbon Registry (ICR)
Audit Analysis
The Migros PV Bundle project in Turkey presents an extremely thin evidentiary record: only a single document of unknown type was extracted with low confidence, and nearly all critical verification fields (additionality, baseline method, VVB identity, monitoring data, permanence mechanisms) are absent. While no material findings or contradictions were reported, the absence of any verifiable additionality test, baseline methodology, or third-party verification makes it impossible to confirm the integrity of the 467,480 tCO₂e claim.
Red Flags
- No additionality test type or VVB verification found in any available document — the project's additionality claim is entirely unverified
- No baseline methodology stated; only a grid emission factor of 0.6261 tCO₂/MWh is recorded, with no reference to a standardised or project-specific baseline approach
- No VVB (Verification Body) identified, no methodology version cited, and no monitoring period or verified ERR reported — the project appears to lack any third-party verification trail
- Leakage deduction is 0% with a justification labelled 'quantified', but no methodology or calculation is available to confirm this is appropriate for a PV bundle in Turkey
- Only one document of unknown type was used for extraction, with low confidence — the evidentiary base is insufficient for any meaningful quality assessment
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2025 | 35,220 | 0 | 35,220 | |
| 2026 | 46,747 | 0 | 46,747 | |
| 2027 | 46,747 | 0 | 46,747 | |
| 2028 | 46,747 | 0 | 46,747 | |
| 2029 | 46,747 | 0 | 46,747 | |
| 2030 | 46,747 | 0 | 46,747 | |
| 2031 | 46,747 | 0 | 46,747 | |
| 2032 | 46,747 | 0 | 46,747 | |
| 2033 | 46,747 | 0 | 46,747 | |
| 2034 | 46,747 | 0 | 46,747 | |
| 2035 | 11,527 | 0 | 11,527 | |
| Total | 467,470 | 0 | 467,470 |
Risk Indicators
No additionality assessment found
No buffer pool; no reversal events but no permanence mechani
0% deduction labelled 'quantified' but no calculation availa
No baseline method stated; only a grid EF of 0.6261 recorded
No FPIC, grievance mechanism, or safeguards documentation fo
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.