Shuangbaotai Animal Manure Management System GHG Mitigation Project in Guangdong Province
Score Breakdown
Integrity
verified Additionality was confirmed by the VVB, and the project uses a combined additionality test under ACM0010 Version 08.0.
missing The monitoring report records numerous corrective-action items, including unclear project start date, baseline alternative concerns, and missing or inconsistent parameter treatment.
Transparency
verified The monitoring period is stated as 2023-04-01 to 2023-12-31, and the VVB is identified as Shenzhen CTI International Certification Co., Ltd.
missing Total ER claimed and verified are not found in the extracted record, and several monitoring and calculation details are left unspecified.
Claim Safety
verified The project reports no reversal events and says leakage is quantified, which is better than leaving leakage entirely unaddressed.
missing Leakage deduction is not stated, the baseline is project-specific rather than clearly standardized, and the record contains contradictions on leakage treatment and crediting period.
Documentation
verified The record includes both a PDD and a monitoring report, with 19 documents used and medium extraction confidence.
missing The monitoring report itself lists many unresolved issues, and key items such as buffer pool coverage, usage monitoring method, and baseline reassessment timing are not stated.
Detailed Analysis
Integrity
The project benefits from VVB-confirmed additionality and a combined additionality test, which supports the core project rationale. On the other hand, the monitoring report contains a long list of unresolved issues around start date, baseline alternatives, investment analysis inputs, and missing monitoring parameters, which weakens confidence in the robustness of the emissions claim. No reversal events are reported, but buffer pool coverage is not stated and leakage treatment is not fully evidenced in the extracted record.
Transparency
The documentation identifies the VVB and monitoring period, which helps traceability. However, total ER claimed and verified are not found in the extracted record, and key MRV details such as usage monitoring method, FNRB method, and several parameter definitions are missing. The extraction confidence is only medium, so the documentation quality is not strong enough to support a high transparency score.
Claim Safety
Claim safety is constrained by the project-specific baseline approach, missing leakage deduction value, and the absence of quantified usage-rate evidence in the extracted record. The project is marked CORSIA-eligible, while CCP status is not stated, so dual-claim risk cannot be ruled out from the available facts. The monitoring report also includes contradictions and multiple methodological clarifications that suggest over-crediting risk may not be fully resolved.
Documentation
The evidence base includes a PDD and monitoring report, and the VVB is named, which is a positive sign for documentation completeness. Still, the monitoring report lists many corrective actions and clarifications, and several important fields are not stated in available documents, including buffer pool percentage, usage monitoring method, and baseline reassessment timing. Medium extraction confidence also indicates at least one key document was not fully readable, limiting reliability.
Overall
I privileged the monitoring report where it was more recent or more specific, but the contradictions still matter: additionality test type differs between documents, leakage treatment is inconsistent, reversal reporting is inconsistent, and the crediting period conflicts across records. Because the monitoring report is the more recent and operationally relevant source, I gave it more weight, but the unresolved discrepancies and extensive corrective actions justify a conservative overall score. The project is not a clear failure, but the evidence quality and claim robustness are only moderate.
Audit Analysis
The project has some positive signs, including VVB-confirmed additionality, no reported reversal events, and documented safeguards such as FPIC and a grievance mechanism. However, the record contains many unresolved methodological and monitoring issues, plus several contradictions that reduce confidence in the claimed emission reductions and the reliability of the documentation.
Project Description
Developer: Profit Carbon Environmental Energy Technology (Shanghai) Co., Ltd. Type: Biogas - Electricity Size: Large Scale Methodology: ACM0010 GHG emission reductions from manure management systems Crediting period: 2020-12-20 → 2025-12-19 Estimated annual credits: 268650 tCO2e SDGs: Goal 7: Affordable and Clean Energy, Goal 13: Climate Action, Goal 8: Decent Work and Economic Growth
Red Flags
- The monitoring report lists many unresolved validation and methodology issues, including unclear start date, inconsistent baseline and investment analysis inputs, and missing monitoring parameters.
- There are contradictions on additionality test type, leakage treatment, and crediting period, which weaken confidence in the project record.
- Leakage deduction is not quantified in the extracted record, and buffer pool coverage is not stated.
- The project is marked CORSIA-eligible, which increases dual-claim scrutiny even though CCP status is not stated.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2020 | 6,035 | 6,035 | 0 | |
| 2021 | 207,349 | 202,160 | 5,189 | |
| 2022 | 51,474 | 50,445 | 1,029 | |
| Total | 264,858 | 258,640 | 6,218 |
Cosa migliorerebbe questo punteggio
- Provide a clean, reconciled emissions package showing claimed versus verified ERs, leakage deduction, buffer pool treatment, and the final crediting period with document-level consistency.
- Resolve the monitoring and validation clarifications by documenting the project start date, baseline rationale, parameter monitoring methods, and the source of all investment-analysis inputs.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed combined test
No reversals reported, buffer not stated
Leakage said to be quantified, value missing
Project baseline, reassessment not stated
FPIC and grievance mechanism present
CORSIA-eligible, CCP status not stated
Where to buy
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Registry Documents
monitoring
- ER-Shuangbaotai Guangdong-1st-V02.xlsx
- MR-Shuangbaotai Guangdong-1st-V03-clean.docx
- MR-Shuangbaotai Guangdong-MP2-V03-clean-16082023.docx
- ER-Shuangbaotai Guangdong-MP2-V02-15082023(1).xlsx
- ER-Shuangbaotai Guangdong-20220630-V03.xlsx
- 04 ER-Shuangbaotai AWMS GHG Mitigation Project in Guangdong Province-V2.xls
- +5 more
Other
pdd
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →