Skip to main content
UCRMaharashtra India.AMS-I.D

1 MW Small Scale Morna Gureghar Hydro Electric Project By M/s Ashoka Sathapatya Pvt. Ltd.

UCR-137 ↗

#398of 421 in Universal Carbon Registry (UCR)#403of 417 in AMS-I.D

2.5/ 10
Integrity
3.0
Transparency
1.0
Claim Safety
3.5
Documentation
2.0

Audit Analysis

This 1 MW small-scale hydro project under the UCR registry has an extremely thin evidentiary base, consisting solely of a Project Design Document (PDD) dated April 2022. No verification report, monitoring report, or VVB assessment is available, leaving additionality, permanence, and emission reduction figures entirely unverified. The jurisdictional baseline and absence of material findings are positive, but the overall record is insufficient to confirm the project's integrity or claim safety.

Red Flags

  • No VVB identified and no additionality test type or verification recorded in any available document
  • No emission reduction figures (claimed or verified) found in the extracted record, making over-crediting risk unassessable
  • Only a single PDD document is available; no verification or monitoring reports exist in the record
  • Buffer pool percentage not stated, leaving permanence risk unquantified for the crediting period

Credit Vintages

Issuance data not yet available — check back soon.

Risk Indicators

Additionality

No additionality test or VVB verification found

Permanence

No buffer pool stated; no reversal events recorded

Leakage

0% deduction, deemed negligible, not quantified

Baseline

Jurisdictional baseline stated; no reassessment date

Safeguards

Safeguards and benefit sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated in record

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-19AMS-I.D.

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents