Audit Analysis
This 1 MW small-scale hydro project under the UCR registry has an extremely thin evidentiary base, consisting solely of a Project Design Document (PDD) dated April 2022. No verification report, monitoring report, or VVB assessment is available, leaving additionality, permanence, and emission reduction figures entirely unverified. The jurisdictional baseline and absence of material findings are positive, but the overall record is insufficient to confirm the project's integrity or claim safety.
Red Flags
- No VVB identified and no additionality test type or verification recorded in any available document
- No emission reduction figures (claimed or verified) found in the extracted record, making over-crediting risk unassessable
- Only a single PDD document is available; no verification or monitoring reports exist in the record
- Buffer pool percentage not stated, leaving permanence risk unquantified for the crediting period
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
No additionality test or VVB verification found
No buffer pool stated; no reversal events recorded
0% deduction, deemed negligible, not quantified
Jurisdictional baseline stated; no reassessment date
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in record
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →