A 5.35 MW onshore wind project in India with a solid jurisdictional baseline and VVB-confirmed investment additionality test. The project delivered approximately 69% of its pro-rata ex-ante expectation over the first 2.5-year monitoring period, indicating conservative crediting. However, 12 material findings during validation (including a transparency gap in the investment analysis) and several unreported parameters (FNRB, usage monitoring, CORSIA/CCP status) limit confidence in the full picture.

Red Flags

  • CAR04 in the validation report flagged that the investment analysis lacked transparency, contained incorrect erection costs, missing purchase orders, and unjustified office/admin costs — all corrected but indicating initial weakness in the additionality case
  • The monitoring report shows verified ERR of 14,213 tCO2e against a claimed 21,444 tCO2e for the same period, a 33% reduction that is not fully explained in the extracted record

Credit Vintages

IssuedRetiredAvailable
2014
14,280014,280
Total14,280014,280

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal risk

Leakage

0% deemed negligible, appropriate for wind

Baseline

Jurisdictional grid EF, standardised

Safeguards

Safeguards mentioned, FPIC/grievance not stated

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25General Methodology v2.1

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents