Biomass based thermal energy generation project by M/S Ginni International Ltd

UCR-227 ↗

#189of 196 in Biomass#410of 421 in Universal Carbon Registry (UCR)#42of 42 in AMS-I.C

2.5/ 10
Integrity
3.5
Transparency
1.0
Claim Safety
3.0
Documentation
2.0

Audit Analysis

This biomass thermal energy project under the UCR registry presents a significant evidence gap: only a Project Design Document is available, with no verification report, monitoring report, or VVB identification. The claimed 32,142 tCO₂e over a 9-year crediting period remains entirely unverified, and key integrity elements such as additionality testing, baseline reassessment, and leakage quantification are absent from the record.

Red Flags

  • No verification report or monitoring report found in the extracted record — the 32,142 tCO₂e claim is entirely unverified
  • No VVB identified and no additionality test type or VVB confirmation found in the PDD
  • Leakage deduction of 0% justified only as 'deemed negligible' without quantification, for a biomass fuel project where fuel-switching leakage is plausible
  • Project-specific baseline with no reassessment date recorded, limiting confidence in the counterfactual

Credit Vintages

Issuance data not yet available — check back soon.

Risk Indicators

Additionality

No additionality test or VVB confirmation found

Permanence

No buffer pool; reversal risk unassessed

Leakage

0% deduction, 'deemed negligible' without quantification

Baseline

Project-specific, no reassessment date recorded

Safeguards

Mentioned but FPIC and grievance mechanism not documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-19AMS-I.C

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents