Electric Vehicle Charger Premier Aggregation
#42of 115 in United States#546of 629 in Verra (VCS)#7of 8 in VM0038
Audit Analysis
The Electric Vehicle Charger Premier Aggregation project has a VVB-confirmed additionality assessment and a conservative credit delivery profile, but is undermined by 12 material findings in the verification report, six outstanding corrective actions, a project-specific baseline with no stated reassessment date, and multiple contradictions across documents. The project's documentation and verification quality fall well below the standard expected for a registered VCS project.
Red Flags
- 12 material findings in the 2025 verification report, including missing verification of AFEC and MPG calculations, missing calibration details for electricity meters, and missing assessment of the impact of project deviations on additionality and baseline
- 6 corrective actions remain outstanding, including the VVB's obligation to submit a complete emission reduction calculation sheet and to justify the monitoring period assessment
- Inconsistent emission reduction values (5,277 tCO2 vs 4,898 tCO2) flagged as a material finding in the verification report
- No buffer pool percentage stated in any available document, leaving permanence risk unquantified
- FPIC was not conducted, and benefit sharing was not described in the most recent verification report despite being mentioned in the original PDD
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 18 | 8 | 10 | |
| 2017 | 115 | 90 | 25 | |
| 2018 | 251 | 229 | 22 | |
| 2019 | 1,268 | 1,246 | 22 | |
| 2020 | 3,771 | 3,603 | 168 | |
| 2021 | 61,001 | 0 | 61,001 | |
| 2022 | 157,533 | 0 | 157,533 | |
| Total | 223,957 | 5,176 | 218,781 |
Risk Indicators
VVB-confirmed but material findings question completeness
No buffer pool stated; no reversal events reported
0% deduction, justification inconsistent across documents
Project-specific, no reassessment date stated
Grievance mechanism present; FPIC not conducted
Not CORSIA-eligible; CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →