Skip to main content
VCSEnergy industries (renewable/non-renewable sources)China Registry: RegisteredACM0002

Gansu Huanghe Chaijiaxia Hydropower Station Project

VCS-435 ↗

#10of 770 in Renewable energy#9of 204 in China#19of 629 in Verra (VCS)#8of 383 in ACM0002

6.9/ 10
Integrity
7.5
Transparency
6.5
Claim Safety
7.0
Documentation
6.0

Audit Analysis

A VCS-registered hydropower project in China with a jurisdictional baseline, VVB-confirmed investment additionality, and no permanence risk (non-AFOLU). The verified emissions reductions match the claimed figure exactly, and the two minor material findings were resolved without corrective actions. Key gaps include unstated CORSIA/CCP status, absent FPIC documentation, and a verification report dated well after the crediting period ended.

Red Flags

  • CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
  • FPIC (Free, Prior and Informed Consent) is not documented in the extracted record despite the project operating in a community-adjacent setting in China
  • The verification report is dated 7 December 2022, more than four years after the crediting period ended on 8 January 2018, raising questions about the timeliness of the verification cycle

Credit Vintages

IssuedRetiredAvailable
2008
154,078154,0780
2009
3,0003,0000
2016
10,000010,000
Total167,078157,07810,000

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Non-AFOLU; no reversal risk

Leakage

0% – negligible for grid-connected hydro

Baseline

Jurisdictional grid EF 0.841

Safeguards

Grievance & benefit-sharing present; FPIC not documented

Double-claim

CORSIA & CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.