9 MW Wind Power Project in Tamil Nadu by ACC Limited
#205of 1935 in Renewable energy#106of 975 in India#121of 1459 in CDM (UNFCCC)#75of 806 in AMS-I.D
Audit Analysis
A straightforward 9 MW onshore wind project in Tamil Nadu under CDM with a jurisdictional grid-emission-factor baseline and a VVB-confirmed investment additionality test. The verification report flagged a corrective action on the clarity of the investment-barrier analysis and three minor findings on monitoring and stakeholder consultation, all of which were addressed. Credit delivery in the available monitoring period ran at roughly 92% of the pro-rata ex-ante expectation, indicating no material over-crediting.
Red Flags
- Corrective Action Request (CAR 1) in the validation report flagged lack of clarity in investment barriers, benchmark selection, and PLF relevance in the initial PDD; corrective actions were required to revise the investment analysis per EB 41 guidelines.
- CL 3 noted that evidence of local stakeholder consultation was not provided during site visits, and the grievance mechanism and FPIC status are not stated in the extracted record.
- The grid emission factor is anchored to 2007 data; no baseline reassessment date is recorded in the available documents.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 21,181 | 0 | 21,181 | |
| 2012 | 18,111 | 0 | 18,111 | |
| 2013 | 21,745 | 0 | 21,745 | |
| Total | 61,037 | 0 | 61,037 |
Risk Indicators
VVB-confirmed investment test, but CAR 1 flagged clarity iss
Avoidance-type wind project; no reversal risk or events repo
0% deduction, deemed negligible — consistent with grid-displ
Jurisdictional grid EF (0.9293, 2007); standard CDM approach
Safeguards mentioned and benefit-sharing described, but FPIC
CORSIA and CCP status not stated in extracted record; CDM cr
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →