Cururos Wind Farm Project
GS-630 ↗ · current registry ID: GS3567
#322of 770 in Renewable energy#2of 8 in Chile#214of 426 in Gold Standard (GS)#242of 383 in ACM0002
Audit Analysis
The Cururos Wind Farm is a Gold Standard wind project in Chile with VVB-confirmed additionality and a recently reassessed baseline, but it carries a heavy load of compliance findings (8 CLs, 4 CARs, 1 FAR, and a FAR#5 exemption) that raise process-integrity concerns. Leakage is set at 0% with no documented justification, and the project is CORSIA-eligible, creating dual-channel risk. The fundamental avoidance mechanism (displacing grid electricity) is sound, but documentation gaps and contradictory reporting across documents weaken confidence in the credit's robustness.
Red Flags
- Eight compliance-list items, four corrective-action requests, one audit finding, and a FAR#5 exemption were raised in the 2025 verification report, indicating significant process non-conformities
- Leakage deduction is 0% with no documented justification in the most recent verification report, despite an earlier (2021) verification report describing leakage as 'quantified'
- CORSIA eligibility is confirmed while CCP status is not mentioned, creating potential dual-channel crediting risk
- Buffer pool percentage is not stated in any available document, leaving permanence risk unquantified
- Crediting period end date is not stated in the verification report, making the full project lifetime and pro-rata ERR assessment impossible
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 90,795 | 90,795 | 0 | |
| 2015 | 176,019 | 167,974 | 8,045 | |
| 2016 | 139,930 | 116,672 | 23,258 | |
| 2017 | 155,697 | 138,808 | 16,889 | |
| 2018 | 159,519 | 142,305 | 17,214 | |
| 2019 | 168,052 | 167,153 | 899 | |
| 2020 | 156,703 | 115,922 | 40,781 | |
| 2021 | 67,588 | 1,196 | 66,392 | |
| 2022 | 130,054 | 130,054 | 0 | |
| 2023 | 121,621 | 0 | 121,621 | |
| Total | 1,365,978 | 1,070,879 | 295,099 |
Risk Indicators
VVB-confirmed investment test
No buffer pool stated; wind project has low inherent reversa
0% deduction with no documented justification in latest repo
Project-specific baseline; reassessed 2023; method contradic
FPIC and grievance mechanism present but FPIC status contrad
CORSIA-eligible; CCP status not mentioned
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →