Fasera TSB Facility 1 is a biomass storage project in Australia with a confirmed investment additionality test and 100-year storage durability, but it carries notable operational and documentation gaps: six material findings with corresponding corrective actions, an unquantified leakage assessment, and a project-specific baseline without a stated reassessment schedule. The verified ERR slightly exceeds the claimed figure, and CCP approval is in place, but the absence of a buffer pool and several missing MRV parameters temper confidence in the credit's robustness.
Red Flags
- Six material findings and six corrective actions reported in the December 2025 verification report, including fuel record-keeping gaps, insufficient gas-monitoring equipment, and a missing calibration protocol for the weather station
- Leakage deduction is not quantified and no justification is provided in any available document, despite leakage being a relevant risk for a biomass storage project
- No buffer pool percentage is stated in the extracted record, leaving permanence risk unmitigated by a standard mechanism
- Additionality test type is inconsistent between the PDD (combined test, September 2024) and the verification report (investment test, December 2025)
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2025 | 2,169 | 2,169 | 0 | |
| Total | 2,169 | 2,169 | 0 |
Risk Indicators
VVB-confirmed investment test
100-yr storage, no reversals, no buffer pool
Not quantified, no justification stated
Project-specific, no reassessment date
Mentioned but FPIC/grievance not detailed
CCP approved, CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →