Dragonfly
#23of 196 in Biomass#3of 5 in Namibia#8of 109 in Puro.earth (PUR)
Audit Analysis
Dragonfly is a Puro-registered biomass storage project in Namibia with a VVB-verified investment additionality test and a 5% permanence deposit, but it is undermined by five cross-document contradictions (notably on FPIC status and additionality test type), three material findings including a missing LCA report, and a leakage treatment that is only 'deemed negligible' without quantification. The verified ERR (1,049.6 tCO₂e) aligns closely with the claimed figure (1,051.4 tCO₂e), suggesting no material over-crediting, but the project's documentation gaps and unresolved contradictions limit confidence in its integrity claims.
Red Flags
- FPIC contradiction: the verification report (Mar 2026) states FPIC was NOT conducted, while the issuance document (Mar 2026) states it WAS conducted — a direct conflict on a fundamental safeguard
- Three material findings in the verification report, including a missing LCA report and diesel usage logs, and unresolved clarification on emission-factor methodology
- Five contradictions across the PDD, verification report, and issuance document covering leakage treatment, additionality test type, crediting period dates, reversal events, and FPIC status
- Leakage is only 'deemed negligible' in the verification report and was not addressed at all in the PDD; no quantified deduction or detailed justification is provided
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2026 | 1,049 | 1,049 | 0 | |
| Total | 1,049 | 1,049 | 0 |
Risk Indicators
VVB-verified investment test
5% deposit, no reversals, buffer pool not stated
Deemed negligible, not quantified, PDD silent
Project-specific, reassessment timing not stated
Grievance mechanism present, FPIC status contradicted
CCP approved, CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →