Grid Connected Wind Power Project by M/s Giriraj Enterprises in Madhya Pradesh
#1015of 1935 in Renewable energy#521of 975 in India#749of 1459 in CDM (UNFCCC)#328of 806 in AMS-I.D
Audit Analysis
A CDM wind power project in Madhya Pradesh with a solid jurisdictional baseline and VVB-confirmed investment additionality, but undermined by five material findings (internal data inconsistencies in the validation report) and a seven-fold discrepancy in claimed emissions reductions between the PDD and the validation report. No monitoring data is available, and several key MRV parameters remain unreported.
Red Flags
- Seven-fold discrepancy in total ERR: the PDD (2019-09-18) reports 167,405 tCO₂e while the validation report (2019-10-18) reports 23,915 tCO₂e; the basis for each figure (single crediting period vs. full lifetime) is not clarified in the extracted record
- Five material findings (CARs) in the validation report flag internal inconsistencies in GHG reduction values, Build Margin, EGBL, crediting-period start date, and EIA notification reference — all requiring corrective action before credit issuance
- No monitoring report or verified emissions reductions are available in the extracted record, making it impossible to confirm actual delivery against the claimed figure
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2015 | 37,233 | 0 | 37,233 | |
| 2018 | 68,836 | 0 | 68,836 | |
| Total | 106,069 | 0 | 106,069 |
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0% deduction, deemed negligible (appropriate for wind)
Jurisdictional grid EF, 2018 reference year
Safeguards mentioned but FPIC and grievance mechanism not do
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →