Guangdong Guanshan Wind Power Project
#111of 770 in Renewable energy#41of 204 in China#131of 629 in Verra (VCS)#79of 383 in ACM0002
Audit Analysis
A 10-year wind power project in Guangdong, China, with a VVB-confirmed investment additionality test and a jurisdictional baseline, but weakened by an inconsistent leakage justification, a 2009 grid emission factor flagged in a material finding, and the absence of FPIC. The ERR figures are internally consistent across the final verification, and the project's renewable nature eliminates reversal risk, but several safeguard and documentation gaps prevent a higher rating.
Red Flags
- Leakage justification is internally contradictory within the same verification report: one section states 'not addressed' while another states 'deemed negligible', leaving the 0% deduction without a clear, consistent rationale.
- The grid emission factor used (0.893325, year 2009) was flagged as incorrect in the monitoring report per the verification report's material findings, requiring correction and ERR recalculation.
- FPIC was not conducted, and the validation report (2010) records no grievance mechanism, no benefit-sharing description, and no safeguards mention — all later contradicted by the 2022 verification report.
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 79,961 | 79,790 | 171 | |
| 2018 | 25,000 | 25,000 | 0 | |
| 2019 | 50,000 | 49,998 | 2 | |
| Total | 154,961 | 154,788 | 173 |
Risk Indicators
VVB-confirmed investment test
Renewable avoidance – no reversal risk
0% deduction, inconsistent justification
Jurisdictional but contradicted; 2009 grid EF
Grievance & benefit-sharing present; no FPIC
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →