Guizhou Jinsha CMM Power Generation Project
#46of 64 in Methane#166of 204 in China#519of 629 in Verra (VCS)#11of 16 in ACM0008
Audit Analysis
The Guizhou Jinsha CMM power generation project has a solid additionality foundation (combined test, legally required capture, VVB-confirmed) but is undermined by five material findings affecting data accuracy, the absence of FPIC and a grievance mechanism, and a thin 0% leakage justification. The project delivered only about 60% of its pro-rata expected emissions reductions for the elapsed monitoring period, raising over-crediting concerns relative to the PDD's lifetime estimate.
Red Flags
- Five material findings in the verification report (generator count, coordinates, electricity price, meter count, and ECPJ data) indicate significant data-quality issues in the project documentation
- No FPIC conducted and no grievance mechanism in place (per the more recent PDD revision of October 2023)
- Verified ERR of 504,229 tCO₂e represents only ~60% of the pro-rata expectation (~843,000 tCO₂e) for the 20-month monitoring period against the PDD's 5,060,210 tCO₂e lifetime estimate
- Leakage deduction of 0% justified only as 'deemed negligible' without quantified analysis, which is thin for a CMM project where flaring or venting could constitute leakage
- Gas capture legally mandated — additionality in doubt
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 128,568 | 23,568 | 105,000 | |
| 2022 | 304,169 | 204,169 | 100,000 | |
| 2023 | 71,492 | 71,492 | 0 | |
| Total | 504,229 | 299,229 | 205,000 |
Risk Indicators
Combined test, VVB-confirmed, legally required capture
Avoidance project, no inherent reversal risk
0% deduction, 'deemed negligible' only
Project-specific, modeled, not yet due for reassessment
No FPIC, no grievance mechanism
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →