8.4 MW Wind Energy Project by Sanwaria Agro Oils Limited, India

CDM-4411 ↗

#648of 1935 in Renewable energy#326of 975 in India#440of 1459 in CDM (UNFCCC)#225of 806 in AMS-I.D

5.5/ 10
Integrity
7.0
Transparency
3.5
Claim Safety
6.5
Documentation
3.5

Audit Analysis

A straightforward 8.4 MW wind project in India with a well-supported investment-test additionality case (IRR below the 11.50% benchmark without CDM revenue) and a jurisdictional grid baseline. However, the available record is limited to validation-era documents from 2011, with no monitoring reports, no verified emission reductions, and low extraction confidence, leaving the project's actual performance unconfirmed.

Red Flags

  • No monitoring reports or verified emission-reduction figures are available despite the crediting period having ended in April 2021
  • Low extraction confidence on at least one key source document, reducing reliability of the extracted data
  • 33 Corrective Action Requests were raised during validation (all subsequently closed), indicating a complex approval process
  • Grid emission factor is from 2008 and no baseline reassessment data is available

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed investment test; IRR below benchmark without C

Permanence

Wind avoidance project; no inherent reversal risk

Leakage

0% deemed negligible; appropriate for grid-displacement wind

Baseline

Jurisdictional grid EF (2008); no reassessment data availabl

Safeguards

Safeguards and benefit-sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25AMS I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents